How do you change duration default to days?

1 reply [Last post]
Dan Harang
User offline. Last seen 8 years 11 weeks ago. Offline
Joined: 31 May 2017
Posts: 2
Groups: None

Hello

I use Powerproject 12 and when I enter the duration for a task and hit enter it defaults to seconds. Is there a way to make the duration column default to days unless another unit is entered?

I've tried formating cells, catogory duration and the time unit day with out result.

Replies

Mike Testro
User offline. Last seen 37 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Dan - Welcome to planning plannet.

Right Click on the top of the duration column.

Select Table definition

Select duration in the dropdown

In the right hand panel find Overide Time Unit and select the one you want.

Best regards

Mike Testro