Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Delayed, but by how much?

3 replies [Last post]
Dominic Planner
User offline. Last seen 24 weeks 1 day ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

Hi all, 

My project has delays and I want to quantify the delay. How do I do this, is it easy to do?

I would like to be able to put a figure forward, is there a report that can be used to demonstrate the delay?

Thanks 

Replies

karim farghaly
User offline. Last seen 3 years 36 weeks ago. Offline
Joined: 10 Dec 2013
Posts: 23
Groups: None

Hi Mike

in P6 i can see the expected finish date on every update 

but, how can i see it in Asta?

Joshua Agyare
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 8 Jan 2009
Posts: 12
Groups: None

Hi, at what stage are you in the project is it running efficient and delayed or is it delayed and not running efficient. If I can know this I will be able to help.

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Dominic

The delay is the difference between the current projected programme completion date and the contract completion date. It will remain an estimate until you have completed the work.

There is no standard report form but it is essential that you follow your contract rules when sending a notice of any delay. And make sure you do it in time.

Best regards

Mike T.