Setting a start date

4 replies [Last post]
James Ball
User offline. Last seen 4 years 41 weeks ago. Offline
Joined: 30 Jan 2018
Posts: 4
Groups: None

Good morning,

Might be a noobie question but I am fairly new to Asta.

I am wondering how to set a line to start on a certain date and not follow the logic.

To put it in context, we can have the gas connection completed after we have removed scaffold but the gas company are booked in for 2 weeks after the scaffold. So the logic on my programme says it will happen right after the scaffold is gone, but I want it to say it is happening 2 weeks after. So when I reschedule it brings it back to after the scaffold.

 

Is there any way of telling Asta the gas connection is happening on a set date?

 

Cheers,

James

Replies

Daniel Zepko
User offline. Last seen 5 years 51 weeks ago. Offline
Joined: 28 Jun 2017
Posts: 7
Groups: None

while a constraint would work, i would suggest adding an activity with the necessary logic for the 2 week lag such as "gas utility availabe to peform hook-up' 

James Ball
User offline. Last seen 4 years 41 weeks ago. Offline
Joined: 30 Jan 2018
Posts: 4
Groups: None

Thansk Mike :) Worked a treat, just what I was after!

James Ball
User offline. Last seen 4 years 41 weeks ago. Offline
Joined: 30 Jan 2018
Posts: 4
Groups: None

Thansk Mike :) Worked a treat, just what I was after!

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi James Welcome to Planning Plant

The easiest way is to put a "Must Start On or After" constraint flag on the task.

Be careful of these because Powerproject does not work on negative float.

Best regards

Mike T.