Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Early Start, Early Finish, Late Start, Late Finish

2 replies [Last post]
Lo Gary
User offline. Last seen 1 year 35 weeks ago. Offline
Joined: 7 Feb 2010
Posts: 49
Groups: None

Dear,

 

 

Could I add these columns in the Gannt Chart?

 

 

 

Regards,

 

Gary Lo

Replies

Mike Testro
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Robert

Haven't heard from you for some time - good to see someone else helping out on the Asta queries.

One small point - you have to rescedule the project to get the results.

Best regards

Mike Testro

Robert Hughes
User offline. Last seen 7 years 40 weeks ago. Offline
Joined: 20 Oct 2006
Posts: 32
Groups: None

Gary,

Yes, you can.

Right click on the title area of the table, hover over Add Column on the menu which appears, and then hover over Float to open a further menu - in this menu you will find Early Start, Early Finish, Late Start and Late Finish. Select one and it will appear in the table area, repeat for the remaining headings.