As Planned Vs As built - Comparison

1 reply [Last post]
Dominic Planner
User offline. Last seen 21 weeks 18 hours ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

Good morning, 

I am looking to compare the as built with the as planned - Is it possible to export this in some format into excel to compare variances in duarations? Or is there an easy way to compare i.e. Planned 5 days, As built 10 days?

Thanks in advance, 

Dominic 

Replies

Yasine Ali
User offline. Last seen 4 years 18 weeks ago. Offline
Joined: 12 Aug 2015
Posts: 18
Groups: None

You could baseline your as planned programme and then insert this in your as built programme.

Then format the chart to show the baseline on its own line which will show you the difference in durations.