Project Manager

Project Manager, UK Ministry of Defence - Directorate of Information and Communication Services, Several Projects

START Date: 
September, 1995
END Date: 
March, 2000

1.     Run competitive procurement projects for call-off contracts for IT Goods and Services.

2.     Manage the resulting contracts during their lifetime to ensure the represent value for money.

3.     Provide an escalation route for any disputes under those contracts.

Program Manager, Project Manager, Project Controls Manager, Department of Main Roads Queensland, Australia, Transport Network Reconstruction Program

START Date: 
May, 1990

PROGRAM MANAGER - Queensland Department of Transport and Main Roads. Reconstruction of Queensland's roads following severe storms and flooding 2009-2012.

PROJECT CONTROLS MANAGER - Gold Ridge gold mine, Sloloman Islands

PROJECT CONTROLS MANAGER - Stacker/Reclaimer shut, Blair Athol Coal, Clermont Queensland

PROJECT CONTROLS MANAGER - Ipswich City Infustructure Project, Ipswich Queensland

PROJECT CONTROLS MANAGER - Kurnel Desalination Plant (450meg), Kurnel Sydney

PROJECT CONTROLS MANAGER - Tugun Desalination Pland (250meg), Tugun Queensland

Project manager, Platinum Technologies, Goil Advantage Project

START Date: 
January, 2006
END Date: 
January, 2010

My core duties included the following

  • Project Planning
  • project scheduling
  • project monitoring and control
  • project evaluatiion

Project manager, Platinum Technologies, Goil Advantage Project

START Date: 
January, 2006
END Date: 
January, 2010

My core duties included the following

  • Project Planning
  • project scheduling
  • project monitoring and control
  • project evaluatiion

Project manager, Platinum Technologies, Goil Advantage Project

START Date: 
January, 2006
END Date: 
January, 2010

My core duties included the following

  • Project Planning
  • project scheduling
  • project monitoring and control
  • project evaluatiion

Project Manager, Several Electric Firms, Numerous Electrical Projects

START Date: 
May, 1998
END Date: 
October, 2007

Electrical schedules for large commerical and industrial projects in the Oklahoma City area.

Project Manager, JE HURLEY Construction, Inc., Multiple government projects

START Date: 
April, 2012
END Date: 
January, 2003

My current scheduling experience includes the following training and software experience:

SureTrak Traing (Colorado State University 2003)

Microsoft Project use to manage construction projects ranging in size of $20k up to $5mil

P6 (NuSolutions 1 week training) and development of company database, management of all company construction schedules.  Starting Jan. 2012.

I would rate myself beginner to average user, but learning at extreme while trying to develop company process and train other PM's for P6 use.

Project Manager, queiroz galvao CONSTRUCAO, Sloug city infrastructure project

START Date: 
February, 1994
END Date: 
April, 2012
  1. Engineer in the technical administration of Benghazi Company for Construction and Reclamation which has prepared designs and technical documents for many projects such as:
  2. Designing pipe line of 15 km in DERYANA
  3. Designing and execute road of 3 km in ALTALHIAH  
  4. Supervise the execution of the administrational building in ALATFAL hospital 
  5. Designing by-way of 7km in BELHNASH  
  6. Preparing contour maps for the reclamation farms of 350 Ha in BESHR 
  7. Executing the project of the administration complex for the textile

Project Manager, queiroz galvao CONSTRUCAO, Sloug city infrastructure project

START Date: 
February, 1994
END Date: 
April, 2012
  1. Engineer in the technical administration of Benghazi Company for Construction and Reclamation which has prepared designs and technical documents for many projects such as:
  2. Designing pipe line of 15 km in DERYANA
  3. Designing and execute road of 3 km in ALTALHIAH  
  4. Supervise the execution of the administrational building in ALATFAL hospital 
  5. Designing by-way of 7km in BELHNASH  
  6. Preparing contour maps for the reclamation farms of 350 Ha in BESHR 
  7. Executing the project of the administration complex for the textile

Project Manager, Self Employed, Various High Rise Residential Buildings

START Date: 
January, 1996
END Date: 
January, 1991

Design & Construction of Residential / Commercial Buildings

      Job Description:     Project Manager (Freelance)