Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Copying Enterprise schedules ..

2 replies [Last post]
Kevin Matthews
User offline. Last seen 14 years 15 weeks ago. Offline
Joined: 21 Jun 2006
Posts: 57
Hello,

I am copying an enterprise structure which has 3 projects in it. When I copy these the enterprise codes don’t copy over and you are left with the projects each having project codes. Am I missing something ?

Keep Planning,

Kevin.

Replies

Kevin Matthews
User offline. Last seen 14 years 15 weeks ago. Offline
Joined: 21 Jun 2006
Posts: 57
Thanks.

Keep Planning.

Kevin.
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Kevin
I stumbled over the same item. EPS codes are not copied by XER.
Primavera replied that this is solved in P6.
Regards
Dieter