XER import error from P6 8.3 to P6 Professional R15.2 without error notification

6 replies [Last post]
oriol manich
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 22 Jul 2011
Posts: 5
Groups: None

Hello folks,

I have a really weird issue. While importing a XER file to Primavera P6 Professional R15.2 (the XER file obtained from an online P6 8.3 through a CITRIX RECEIVER platform) the import process starts with the loading and suddenly stops, with no error or exception window popping up.

I have no clue about the cause.

Can anyone help?

Thanks.

Regards,

Replies

Zoltan Palffy
User offline. Last seen 15 weeks 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

robert make sure that you have the proper rights set on your laptop

Robert Varghees
User offline. Last seen 7 years 38 weeks ago. Offline

IMPORT ERROR in 15.1 version p6

 

Hi, i am importing .xer from 15.1version to my laptop but i am unable to retrive my cost and budgeted units . Since both are same version why i am getting error. Could anybody can help. I have tried to import why XML format also and gave error with log details.

please help if any bodyhave encountered same problem.

Thanks & Regards

RV

Zoltan Palffy
User offline. Last seen 15 weeks 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

use the p6 excel parser and bring it into the parser then rebuld the xer file in the parser

here is the link to the parse

https://www.planacademy.com/how-to-clean-an-xer-file-using-the-parser/

https://planacademy-nffybkc1gjvuuhit.netdna-ssl.com/wp-content/uploads/2012/01/xerFileParserBuilder_2007.xlsm

 

Dear all,

 

I have problem in importing xer p6 file.

Error occur "CVRCU-1939-9  Default value  provided for field ev_compute_type is not valid"

Waiting for your inputs.

 

COCOY

oriol manich
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 22 Jul 2011
Posts: 5
Groups: None

Hello Zoltan,

I already tried and also a colleague imported that same file successfuly so we ruled out that the file is corrupt.

Thanks

Zoltan Palffy
User offline. Last seen 15 weeks 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

down load the xer from the citrix server agian it may be corrupt