Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Logic errors after Updating from an XER Import

3 replies [Last post]
Mike Thornley
User offline. Last seen 14 years 2 weeks ago. Offline
Joined: 30 Sep 2005
Posts: 6
Groups: None
I have found that after importing an XER file to Update an existing Project some logic changes occur. These have lead to loops, which hightlighted the problem otherwise I may never have discovered the logic changes.

Has anyone else found this happening? Do you know what causes the problem? How do I avoid it happening?

The only way I can trust an import is to replace the existing project but then I loose the filters on Project Codes.

Replies

Kevin Button
User offline. Last seen 2 years 18 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Mike

It might be worth checking your Import Configuration Options. The online help on this area suggests that for the Activity Type data you need to select the ’Update Existing’ action and tick the Delete box. Unless I am mistaken this should remove any existing relationships and replace them with those in the xer file being imported.

Cheers
Mike Thornley
User offline. Last seen 14 years 2 weeks ago. Offline
Joined: 30 Sep 2005
Posts: 6
Groups: None
P3e version 4
Bill Guthrie
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
what program are you using