No change in scheudule after "Update Existing" xer import

3 replies [Last post]
wullie hendry
User offline. Last seen 8 years 16 weeks ago. Offline
Joined: 14 Oct 2014
Posts: 8
Groups: None

I update a subcontractors schedule every week and normally everything goes OK.  I have been doing this for over 1 year every week with the same settings and had no problems until around 6 weeks ago.  Now when I import the xer nothing changes, I do not receive any error to notify me and the import appears to be normal until checked.  When I import the xer as a new file I can see the update has been done correctly. 

 

This problems occurs with version 7 "update existing" import.  I have not (nor has he) changed the version etc or any other factor that may affect the import. 

 

Has anyone else encountered this?  I can not figure out why this is happening. 

 

Thanks in advance

 

 

   

Replies

Zoltan Palffy
User offline. Last seen 9 weeks 23 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

check the import settings change ALL of the setting to insert new

also if this is on a server make sure that your access rights did not change

wullie hendry
User offline. Last seen 8 years 16 weeks ago. Offline
Joined: 14 Oct 2014
Posts: 8
Groups: None

Zoltan

 

As stated the settings have been the same for over a week.  

 

The import does say it has completed and nothing changes hence the reason I have a problem.!

Zoltan Palffy
User offline. Last seen 9 weeks 23 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

I am confused you say nothing changes and then you say the update has been done correctly 

double check the import settings