Progress reporting

PLANNING ENGINEER, Bechtel international Inc., QC LNG Project

START Date: 
September, 2011
END Date: 
February, 2012

 

 

·         QC LNG is a multibillion-dollar EPC contact won by OG&C on Feb 5, 2010 - possibly the largest Lump Sum Turn Key LNG job that Bechtel has taken on!

PLANNING ENGINEER, Chevron , Gorgon LNG Downstream Project

START Date: 
February, 2012
END Date: 
December, 2012

 

The Greater Gorgon Area is located 200km offshore of the northwest coast of Western Australia and contains in excess of 40 trillion cubic feet of recoverable natural gas.

·         16.5m Manhours (EPC)

·         200K Tonnes overall

·         97K Tonnes of structure steel

PLANNING ENGINEER, HHI, QATAR GAS II (ONSHORE PROJECT LNG STORAGE 5 TANKS)

START Date: 
July, 2007
END Date: 
December, 2007

 

140,000 m³ the tanks have an outer diameter of 78 m and are about 40 m high. The 80 cm thick walls are horizontally post-tensioned using 19x0.62" while12 strand tendons Ø 0.62" were used for the vertical post-tensioning.

 

- Monitoring actual of progress comparing with BOQ 

- Maintain and update Project schedule

- Work variation and forecast volume 

- Project S-Curve, Milestone schedule, 3 week look ahead program

- Critical Shipment follow up and recovery plan preparation

Senior Planner, EMAS, Lewek Constellation

START Date: 
May, 2012
END Date: 
July, 2012

A really short stay with EMAS-AMC company.

The copmany is one the largest in Singapore and I was managing Lewek Constellation, The Lewek Constellation is an ice-class, DP3, multi-lay vessel with heavy lift capabilities. It has superior maneuverability and a high transit speed with a multi-lay system that can support both rigid and non-rigid pipelines.The vessel has a 3,000 MT heavy lift crane that includes Active Heave Compensation capabilities.

 

Exposure wise are as follows:

1. Shipbuilding industry

Lead Planner, FMC Technologies, CNOOC LiuHua, GWF, Shell Prelude

START Date: 
April, 2011
END Date: 
May, 2012

A short less than 1 year stay with FMC Technologies, the No.1 Most Admired Equipment O&G Company. Having global offices in Houston, Norway, Brazil, Singapore.
 

During this time,

1. Exposed to Subsea Equipment. Totally different from my topside construction experience 

2. Exposed to Manufacturing planning methods from project standpoint.

3. Teach engineers how to read schedules, especially usnig floats as a guide.

4. In-depth understading of the constraints and right application.

Project planner, Scantec Personnel Limited, Nuclear

START Date: 
January, 2012

Experienced in both MSProject and Primavera. Duties include producing baseline plans, scheduling tasks within operational facilities, progress updates (monthly & adhoc), reporting. Full security clearance

Planning Manager, Chicago Maintenance & Construction Co LLC, Schools, Villas

START Date: 
December, 2010

Establishing the Planning Department including resourcing, implementing policies, procedures etc.

Supervision of Planning Engineers and reviewing their works.

Responsible for preparing and reviewing baseline schedules for all the projects of the company.

Pre - Award Project Management

Risk Analysis for all the projects

Progress Review and Critical Path Analysis

Determination of recovery schedules to mitigate delay.

Review/Assist in preparation of EOT by planning engineers

Productivity Analysis and review.

Planning Manager, Chicago Maintenance & Construction Co LLC, Schools, Villas

START Date: 
December, 2010

Establishing the Planning Department including resourcing, implementing policies, procedures etc.

Supervision of Planning Engineers and reviewing their works.

Responsible for preparing and reviewing baseline schedules for all the projects of the company.

Pre - Award Project Management

Risk Analysis for all the projects

Progress Review and Critical Path Analysis

Determination of recovery schedules to mitigate delay.

Review/Assist in preparation of EOT by planning engineers

Productivity Analysis and review.

Planning Manager, Chicago Maintenance & Construction Co LLC, Schools, Villas

START Date: 
December, 2010

Establishing the Planning Department including resourcing, implementing policies, procedures etc.

Supervision of Planning Engineers and reviewing their works.

Responsible for preparing and reviewing baseline schedules for all the projects of the company.

Pre - Award Project Management

Risk Analysis for all the projects

Progress Review and Critical Path Analysis

Determination of recovery schedules to mitigate delay.

Review/Assist in preparation of EOT by planning engineers

Productivity Analysis and review.

Planning Manager, Chicago Maintenance & Construction Co LLC, Schools, Villas

START Date: 
December, 2010

Establishing the Planning Department including resourcing, implementing policies, procedures etc.

Supervision of Planning Engineers and reviewing their works.

Responsible for preparing and reviewing baseline schedules for all the projects of the company.

Pre - Award Project Management

Risk Analysis for all the projects

Progress Review and Critical Path Analysis

Determination of recovery schedules to mitigate delay.

Review/Assist in preparation of EOT by planning engineers

Productivity Analysis and review.

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Syndicate content