Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

PLANNING ENGINEER, HHI, QATAR GAS II (ONSHORE PROJECT LNG STORAGE 5 TANKS)

START Date: 
July, 2007
END Date: 
December, 2007

 

140,000 m³ the tanks have an outer diameter of 78 m and are about 40 m high. The 80 cm thick walls are horizontally post-tensioned using 19x0.62" while12 strand tendons Ø 0.62" were used for the vertical post-tensioning.

 

- Monitoring actual of progress comparing with BOQ 

- Maintain and update Project schedule

- Work variation and forecast volume 

- Project S-Curve, Milestone schedule, 3 week look ahead program

- Critical Shipment follow up and recovery plan preparation

- Evaluate and produce Weekly progressive report, manning report

  Monthly progressive / Critical milestone report and update P3

- Scheduling time period of bid proposal.