Manager of Systems, Synchronal Corporation, Office Automation, Corporate Accounting and Media /Broadcast Tracking

START Date: 
May, 1987
END Date: 
August, 1988

Responsible for Daily Computer Operations, End-User Computing and Facilities Management. Implemented an Office Automation program. Developed corporate computer requirements. Provided budgets and work plans. Created the End-User computing group and its project development and training methods. Developed staffing requirements and justifications, interviewed- hired - coordinated DP staff and consultants. Negotiated equipment leases and provided pre-installation facility preparation. Developed RFPs for Corporate Accounting System and Media/Broadcast Programming System.

Experience Hours (Planning & Scheduling): 
500
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
500

Senior Planning Manager, ARCADIS Middle East, Al Rajhi Bank Headquarter - Tower building

START Date: 
December, 2015
END Date: 
March, 2017

ARCADIS, (Former EC Harris), Riyadh / KSA, Nov 2015 to Feb 2017

Consultant, www.arcadis.com

 

Planning Manager

·  Preparing Strategical Master Programandcontrolling the subcontractor programs, monitoring progress.

·  Conducted basic analysis of extension of time (EoT) claims.

Planning and Cost Engineer, Amecfosterwheeler, Abudhabi, Zora Project, Danagas Sharjah

START Date: 
January, 2015

Seconded to Danagas Sharjah as planning and cost engineer for Zora offshore field developement Project.

  • Act as integrated Project Controls engineer for the Zora Project
  • Cost Control and analysis
  • Assist in obtaining third party certification of project expenditure for project funding.
  • Monitor all EPC Contractors schedule and costs, Analyse project performance and report variances from project goals.
  • Consolidate and prepare Project monthly reporting to management with S curves.
  • Advice on cost overrun and new budget requirements
Experience Hours (Planning & Scheduling): 
750
Experience Hours (Cost Management): 
2000

Planning and Cost Engineer, Amecfosterwheeler, Abudhabi, Zora Project, Danagas Sharjah

START Date: 
January, 2015

Seconded to Danagas Sharjah as planning and cost engineer for Zora offshore field developement Project.

  • Act as integrated Project Controls engineer for the Zora Project
  • Cost Control and analysis
  • Assist in obtaining third party certification of project expenditure for project funding.
  • Monitor all EPC Contractors schedule and costs, Analyse project performance and report variances from project goals.
  • Consolidate and prepare Project monthly reporting to management with S curves.
  • Advice on cost overrun and new budget requirements
Experience Hours (Planning & Scheduling): 
750
Experience Hours (Cost Management): 
2000

Planning Engineer/Schedule Controls, Mace International Ltd, Black Sea Hotel and Residence

START Date: 
February, 2014
END Date: 
February, 2015

Experienced in Planning, Scheduling, Monitoring and Reporting, Project Management, Programme Management and Construction Management for High Rise Building and Apartments, 5 Star Hotels Development, Retails Development, Utilities and Infrastructures, Port Development, Cement Plant Project and Power Plant Projects.

 

 

CURRICULUM VITAE – SHAMSUHAIME AHMAD

 

1.

Experience Hours (Planning & Scheduling): 
30000
Experience Hours (Cost Management): 
6000
Experience Hours (Forensic Analysis): 
4000

Project Controls Scheduler, CH2MHILL, IDRIS

START Date: 
June, 1998

Basically  I am a civil Engineer completed graduate diploma in Project management with an over 13 years of extensive experience in Project Planning, scheduling, monitoring & controls, his multi skill sets in the field of construction supervision, project management and cost engineering always supporting to realize and approach to develop a workable plans and controls for projects he handled.  I am  worked in diversified projects pertaining to the repair rehabilitation, operation & maintenance of waste water facilities, Engineering Procurement and Constr

Project Controls Scheduler, CH2MHILL, IDRIS

START Date: 
June, 1998

Basically  I am a civil Engineer completed graduate diploma in Project management with an over 13 years of extensive experience in Project Planning, scheduling, monitoring & controls, his multi skill sets in the field of construction supervision, project management and cost engineering always supporting to realize and approach to develop a workable plans and controls for projects he handled.  I am  worked in diversified projects pertaining to the repair rehabilitation, operation & maintenance of waste water facilities, Engineering Procurement and Constr

Planner, Fletcher Construction Company Ltd, Christchurch housing post-disaster reconstruction

START Date: 
December, 2010

 

Employer

Fletcher Construction EQR

Position

Works Planner reporting to Works Manager at Addington Hub

Dates

December 2010 to Present

Project

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.