EOT Claims

Planning Engineer, Al-Ayuni Investment & Contraction CO, Riyadh, KSA, CTW-400, SAR Railway Project (Riyadh-Qaseem)

START Date: 
September, 2010
END Date: 
June, 2011

 

 Revised & got approval of Working Schedule Using Primavera P6.

Recorded the Delays Due to hold Areas & Claimed EOT.

Updated the Progress, Analyzed Delays & advised the solutions.

Evaluate Delay impact for Land Acquisition issues & prepared the revised Baseline.

Prepared the Resource histograms (Manpower/ Equipment) & Project Cash Flow.

Monitored & Managed Resources (Manpower & Material)

Progress Meetings with Consultant & Client

Claims Analysis Planner, Marconi, northern line upgrade -London underground

START Date: 
February, 1995
END Date: 
February, 1997

Northern LIne project. Claims analyst . Ms project. as planned impacted . as planned v as built. LOndon underground working for Marconi on communications. Claim recovery attained. Did not proceed to formal dispute.

Claims, EAst midlands electricity, Confidential

START Date: 
February, 1992
END Date: 
February, 1994

East Midlands Electricity claims analysis on projects. Rectrospective work. simple programmes.

Delay, Drake and Scull, Jubilee Line Extension

START Date: 
February, 1992
END Date: 
March, 1994

Claims analysis on Jubilee line project. Delay and disruption. Claims analysis.

Senior Planner, Larsen & Toubro Limited, Kakrapar Atomic Power Project, Kudankulam Nuclear Power Project

START Date: 
July, 2008

Scheduling and project control

Performing Time Impact analysis

Cost & Schedule integration

Experience Hours (Planning & Scheduling): 
3300
Experience Hours (Cost Management): 
2200

Junior Scheduler/Planner, Doosan Heavy Industies and Construction Co. Ltd, 1X660MW SUPER CRYTICAL THERMAL POWER PROJECT

START Date: 
February, 2012

Cirebon Project(Forensic Schedule Analysis),

 

For Claim, with forensic schedule analysis which is named time impact analysis I did calculate EOT.

Claims Specialist, NORTH LUZON RAILWAY CORPORATION, North Luzon Railway Project Section I Phase I

START Date: 
March, 1987

 

Date                       :           December 11, 2008 to Present

Employer             :               NORTH LUZON RAILWAY CORPORATION

PLANNING ENGINEER, Turcon Pvt Ltd, Multiple clients

START Date: 
August, 2008
END Date: 
February, 2010

 

PLANNING

Senior Planner, BAM Nuttall, Various

START Date: 
December, 2003

I carry out a planning role with involvement on all schemes within the midlands business unit area.

Senior Planning Engineer, Saudi Oger Limited, Various projects

START Date: 
September, 2009
END Date: 
December, 2011

As a Senior Planning Engineer, I handle Planning Engineers, initiate and plan actions for planning and scheduling works to be done, prepare baseline schedules, maintain schedules, monitor projects and prepare reports of the status of all on-going projects of PPCD to the Top Management of the company, prepare PPCD Division planning and scheduling standards, prepare Earned Value Management Plan and Reports, prepare Manpower Monitoring Management Plan, prepare EOT analysis, and attend meetings, among others.

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Syndicate content