Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

%100 Project Planning; Cost control; Budgeting; Performance Monitoring; Project Control; Primavera P6

Planner/Project Coordinator, SP&MS Ltd, General, Baglan Bay Power Station

START Date: 
April, 2002
END Date: 
February, 2005

Swansea Planning & Management Services Ltd.

 

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
250

Regional Project Planning & Controls Manager, General Electric Company (GE), All Regional Projects

START Date: 
February, 2005
END Date: 
July, 2011

General Electric (Granite Services International) – Power Generation Services

3 Defined Responsibilities throughout tenure:

Experience Hours (Planning & Scheduling): 
18300
Experience Hours (Cost Management): 
8000
Experience Hours (Forensic Analysis): 
1000

Senior Planner, CTEC, Merredin Power Station, West Angeles Power Station

START Date: 
July, 2011
END Date: 
January, 2012

CTEC Pty Ltd:  Senior Project Planning & Controls – Merredin Power Station – Greenfield Site

 

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
900
Experience Hours (Forensic Analysis): 
500

Senior Planner, O'Donnell Griffin, All Great Western Region Projects

START Date: 
January, 2012
END Date: 
May, 2012

O’DONNELL GRIFFIN:   Senior Project Planner/Asst PM – Brockman 4 Phase 2 Expansion Project (FIFO) – project upwards of AUD$20mm

 

Experience Hours (Planning & Scheduling): 
900
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
250

Senior Integrated Planning Lead, GE Oil & Gas, GORGON LNG Project, Fabrication of Subsea Manifolds and Associated Equipment for the Julimar Project.

START Date: 
January, 2013
END Date: 
June, 2015

GENERAL ELECTRIC OIL AND GAS: Subsea Systems/Offshore Projects

Integrated Project Planning Lead – Australia and Pacific Asia

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
900

4D Planning Consultant, MAC Constructions,, Sulphur Recovery Project

START Date: 
April, 2001
END Date: 
September, 2002

During this period I was involved as a Planning Engineer for Sulphur Recovery Project in Saudi Aramco. Worked as Planning Engineer under MAC Construction (main subcontractor for Technip) and involved in execution of Multi discipline Civil Buildings, Mechanical, Electrical, Instrumentation, Insulation and Painting works for two new Sulphur Recovery Unit at Saudi Aramco Riyadh Refinery. 

4D Planner, Siemens, Al Khafji Joint Operation Saudi Arabia

START Date: 
March, 2004
END Date: 
April, 2005

Involved in Al-Khafji Joint Operations’ (KJO) project; KJO, a partnership between Kuwait Gulf Oil Company (KGOC) and ARAMCO Gulf Operations Company (AGOC), The project involves major Infrastructure development of Khafji area and the project comprises of various Roads, Bridge, Power stations, Storm water drainage, etc.

The entire Project Control Team was co-located in one office under M/s Dar Al-Handasa (PMC) for the Master Plan development and to handle the following major projects;

planning and cost control, HESTON - KNPC, A variety of oil and gas

START Date: 
February, 2014

I'm Senior Planning and Cost Control Engineer for Oil and Gas Fabrication Facilities and Cosntruction Sitesm Refineries.

Consultant Planning and Project Controls Manager, Surbana Jurong Consultants Pte. Ltd, VIA major airport expansion program

START Date: 
December, 2017
Project Controls Head Senior Principal Planning Manager For an Airport Major Expansion Program in Maldives
Experience Hours (Planning & Scheduling): 
300
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
100

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content