4D Planner, Siemens, Al Khafji Joint Operation Saudi Arabia
START Date:
March, 2004
END Date:
April, 2005 Involved in Al-Khafji Joint Operations’ (KJO) project; KJO, a partnership between Kuwait Gulf Oil Company (KGOC) and ARAMCO Gulf Operations Company (AGOC), The project involves major Infrastructure development of Khafji area and the project comprises of various Roads, Bridge, Power stations, Storm water drainage, etc.
The entire Project Control Team was co-located in one office under M/s Dar Al-Handasa (PMC) for the Master Plan development and to handle the following major projects;
- Community Housing, Facilities & Bachelor’s Quarters
- Office Park and Warehouse
- Switching Stations
- Two Causeway Bridges
- Utilities, Roads & Landscaping Works: Involves relocation of major utilities such as 33kv, 11kv, DI Waterlines, etc. and the new Highway construction of 15 KM with two lane carriage way in each direction.
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: