Senior Planner engineer

Senior Planner engineer, Technical Office Engineer, Egypt, SIAC, AMRAN Cement Plant Project, EZZ flat Steel Project, Smart Village & Beverly Healz Projects in Egypt

START Date: 
November, 1999
END Date: 
July, 2004

SIAC ( Egyptian Company )From 15 Nov 1999 till 15 July 2004

a) From 1 Nov 2002 till 8 July 2003 in Smart Village & Beverly Healz Projects in Egypt

Smart Village was one building consists of basement + ground + 5 typical floors, area of one floor about 4,000 m2 the project value about 20,000,000 Egyptian Pounds.

Beverly Healz is under ground sewerage lines with project value about 15,000,000 Egyptian Pounds.

My Duties:

·  Build the time schedule (Base Line Program) and Recovery if required

·  Reso

Senior Planner engineer, ACC, ALRAWDH Palace In AL AIN, UAE

START Date: 
June, 2006
END Date: 
March, 2007

Arabian Construction Company(ACC in UAE) From 5 Jun 2006 Till 1 Mar 2007 as Senior Planning Engineer in Project ALRAWDH Palace In AL AIN, UAE

Project Value is 560,000,000 Dhs

My duties are :

·  Develop base line programs

·  Load resources such as manpower, cost, …….

·  Weekly and monthly reports

·  Develop recovery program if required

·  Follow up the site progress and update<

Senior Planner engineer, Vinci Contruction Grands Projets, Lusail LRT

START Date: 
November, 2009
END Date: 
December, 2009

 

Construction of the time schedule of Lusail Railway Transit System:

 

  • Establishment of the Work Breakdown Structure (WBS=GBSxPBSxABS);
  • Creation of the time schedule of the project (3000 tasks), Gantt & trip diagrams, in the time allowed (40 days).

Senior Planner engineer, Collins Project Delvery for Enterprise Plc, London Underground Power Upgrades

START Date: 
September, 2009
END Date: 
October, 2010

  

Preparation of Tender Programme for LUPU 6 - Installation of 132kV HV Cable with associated route including Civil’s Elements and Bored Main Highways Crossing with associated Design, Procurement, Earthing & Bonding, and Cabling works.

Preparation of Tender Programme for Hammersmith Depot DC Power Upgrades - Track Isolation Switch installation with associated Design, Procurement, Installation of Civil bases, Earthing & Bonding, and Cabling works.

  • Preparation/Creation of P3e Integrated Master Program
    • Creation, Modification and Assi

Senior Planner engineer, Patel enginneering Ltd, Tunneling, Water treatment & SWD works

START Date: 
November, 2005

Sr. Planning engineer.

Good knowledge of planning softwares like MSP-07, P6, Candy, with ERP like Oracle apps & Build Smart.

Can handle EPC & TC types works Independently.

My work areas are Project planning, Scheduling, Monotoring, controlling & Reporting, Risk anlysis.

Senior Planner engineer, Balfour Beatty Major Projects, 1.M25 Motorway Widening J16 to J23

START Date: 
February, 2009

Current Role

The Highways Agency is widening approximately 102 kl of M25 by adding a lane in each direction to make generally a 4 –lane Motorway.

Senior Planner engineer, 2ER Engneers & Consultants, Railway, M&E and Heavy Civils

START Date: 
January, 2004

7years experience in planning, scheduling and control.  I have experience in various fields ranging from Railway, M&E and Heavy constrution.

Senior Planner engineer, Shaw Stone & Webster, YANSAB OLEFIN PLANT

START Date: 
October, 2008

Prepared the re-baseline of the original schedule of >7,500 activities, including claims analysis, critical path analysis, forensic documentation, new histograms, and curves to be approved by theclient.Prepare turn over schedules& commissioning schedules . Integrated the contractors’ schedules to the main project schedule. In charge of creating the system schedule (turnover schedule) for a one thousand million dollar project.

Senior Planner engineer, Assistant Planning Engineer, Civil construction planning engineer, Agip KCO,Bechtel international, Japan Gas Co. Corporation (JGC-Japan), "Bechtel, Technip, Fluor Daniel, Tecnimont, Lurgi & Linde", Roads %26 Infrastructure, Power

START Date: 
August, 1990

Establish and manage effectively a planning and progress control system in order to support the Project Manager's decision-making process and allow him to complete the project according to the internal baselines and in compliance with the contractual dates and requirements. Ensure any deviation from plan is promptly spotted and analyzed, final time impact is estimated and the effect of corrective actions taken is monitored. Create a schedule awareness atmosphere among all project participants.