Smart Village & Beverly Healz Projects in Egypt

Senior Planner engineer, Technical Office Engineer, Egypt, SIAC, AMRAN Cement Plant Project, EZZ flat Steel Project, Smart Village & Beverly Healz Projects in Egypt

START Date: 
November, 1999
END Date: 
July, 2004

SIAC ( Egyptian Company )From 15 Nov 1999 till 15 July 2004

a) From 1 Nov 2002 till 8 July 2003 in Smart Village & Beverly Healz Projects in Egypt

Smart Village was one building consists of basement + ground + 5 typical floors, area of one floor about 4,000 m2 the project value about 20,000,000 Egyptian Pounds.

Beverly Healz is under ground sewerage lines with project value about 15,000,000 Egyptian Pounds.

My Duties:

·  Build the time schedule (Base Line Program) and Recovery if required

·  Reso