Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

PLANNING COORDINATOR

PLANNING COORDINATOR, Ledcor, Shell MRM - Various Projects

START Date: 
February, 2012
END Date: 
April, 2013
  • Compiled Field Installation Work Packages (FIWPs) that included scope of work, latest revision engineering drawings and documents, scheduling, and all pertaining safety and quality information in order to optimize construction execution through enhanced preparation and detailed planning
  • Using superintendent input and field feedback, developed a standardized template from which all FIWPs could be developed
  • Assisted with the planning and development of projects including - preparation of execution plans, work sequencing, budget estimates and level 6 schedules
Experience Hours (Planning & Scheduling): 
3050

Planning Coordinator, BLUE STAR LIMITED, Calcutta (India), Head Office & Sustaniable Development Projects

START Date: 
November, 1995
END Date: 
August, 2001

Works closely with customers to interpret and convert defined requests into

more clearly defined scopes of work, including general definition of labor, materials

and equipment needed to do the job.

 

Works closely with Procurement Department to create requests for proposals, establish timelines, answer questions and select vendor; develops related payment

schedules and monitors work progress.

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
250

Planning Coordinator , FOSTER WHEELER ENERGY LIMITED, PETRONAS Second Refinery ( PSR- 2 Revamp) Sg. Udang Melaka Malaysia

START Date: 
February, 2009
END Date: 
February, 2007

Employer           : FOSTER WHEELER ENERGY LIMITED

Position             : Planning Coordinator

Project Title       : PETRONAS Second Refinery ( PSR- 2 Revamp)
Based                : Sg. Udang Melaka Malaysia
Project Valued   : USD 1.1 Billion
Project Phase Worked: Execute and Operate

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
40000

Planning Coordinator , FOSTER WHEELER ENERGY LIMITED, PETRONAS Second Refinery ( PSR- 2 Revamp) Sg. Udang Melaka Malaysia

START Date: 
February, 2009
END Date: 
February, 2007

Employer           : FOSTER WHEELER ENERGY LIMITED

Position             : Planning Coordinator

Project Title       : PETRONAS Second Refinery ( PSR- 2 Revamp)
Based                : Sg. Udang Melaka Malaysia
Project Valued   : USD 1.1 Billion
Project Phase Worked: Execute and Operate

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
40000

Planning Coordinator , FOSTER WHEELER ENERGY LIMITED, PETRONAS Second Refinery ( PSR- 2 Revamp) Sg. Udang Melaka Malaysia

START Date: 
February, 2009
END Date: 
February, 2007

Employer           : FOSTER WHEELER ENERGY LIMITED

Position             : Planning Coordinator

Project Title       : PETRONAS Second Refinery ( PSR- 2 Revamp)
Based                : Sg. Udang Melaka Malaysia
Project Valued   : USD 1.1 Billion
Project Phase Worked: Execute and Operate

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
40000

PLANNING COORDINATOR, SENER INGENIERIA Y SISTEMAS, (various projects)

START Date: 
December, 2015

Planning Coordinator for Madrid Office for awarded and on bidding phase Projects

PLANNING COORDINATOR, General Electric Company (GE), Compressor Module Project for the P-56 Semi-sub oil & gas rig

START Date: 
August, 2008
END Date: 
October, 2009

Project Management  - Planning / Project Coordinator, August 2008 – October 2009

Coordination of financial and physical Planning and Control for Engineering, Procurement, Construction & Assembly related to Timing, Cost & Performance Indicators of the P-56 EPC Contract.

Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
500

PLANNING COORDINATOR, PFB d.o.o., Construction of residential and commercial buildings - II phase WEST65

START Date: 
February, 2015

Coordination of planning and control of construction of residential and commercial buildings

PLANNING COORDINATOR, COEG, Rnest Pipelines

START Date: 
August, 2012

Poli pipelines 7 km diameters 8 to 46 inches conecting the port to Petrobras refinery cerca US$400 million project

Coordination of Plannig team

Measurement analyses

fisical and finacial curve Follow up

Follow up of manpower and equipmen schedule

Forecast reports

PLANNING COORDINATOR, Mancon Consutlancy and Project Management , Mantrac Takoradi New Facility-Ghana

START Date: 
July, 2012
END Date: 
June, 2013

* Preparing master and detailed time schedule (using primavera P6 and MS Project).
* Coordination with design team to prepare tender package
* Evaluation and awarding of contractors.
* Preparation of contract agreements complying with FIDIC standards.
* Preparation of projects budget.
* Following up construction phase (time and cost).
* Coordination with different project parties (emails - meetings).
* Document controlling (project documents - historical data - lessons learned)

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content