Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Asta Powerproject

Copying Links

Hi all,

 

Is it possible to copy links from one task to another?

 

i.e. I have a task that has a lot of finish to start links coming from it, I've created another task  and want to give it the same successors. Is this possible, without manually creating each link?

 

Thanks in advance,

 

Chris

Asta PP resource usage plan

Enclosed please find a link to a resource leveling test schedule as to compare how different software handle the resource allocation. 

http://www.mediafire.com/view/u9s6qk45pjn9q6t/j3013_8_1.xml

Display Activity Steps in Asta from P6

Hi colleagues,

I have a project created in Primavera P6 with some activites with activity steps.  I opened this project in Asta Powerproject but I can't find a way how can I display the activity steps I created in P6.

Please help me how could I show it in Asta.  Thank you.

 

Best regards,

Leonard

Equivalent Physical % Complete Coumn from P6 into Asta

Dear colleagues,

I tried to open a project from P6 with Physical % Complete update in Asta Powerproject, but may I know what particular column in Asta that is equivalent to this?

Best regards,

Leonard

Planned / Actual % Complete S-Curve

Morning all,

 

Just trying to do a very basic planned vs actual percent complete S-Curve.


Any idea how it's done?

 

I just want to show the variations between the two.


Kind regards.

Automatics resource levelling Asta

Dear Asta users,

I don’t know whether you noticed, but I started an initiative to compare automatics resource levelling of different tools.

http://www.planningplanet.com/forums/planning-scheduling-programming-discussion/574396/comparison-resource-levelling-algorithms-di

Would anybody of you be interested to contribute to this initiative?

Top Down Forecast Entry (Manual)

Afternoon All,

Hoping you can help me out please.

I am trying to work out how to manually enter forecast & budget values per month. I am happy with bottom up forecasting but more often than not the clients cost engineer creates a monthly rolling forecast (in Excel) that then needs plugging into project/primavera/asta each month against some high level (often WBS level) bars.

Happy with doing this in everything but Asta, so any wisdom on how this can be achieved in Asta would be fab.

Thanks in advance. Adam.

Asta - Draw curve if vertical

Hello All,

 

Hope you all had a great and rested weekend. A programme has been set to draw curve if vertical by default so everytime i draw a link between 2 tasks, the link will become curve automatically if its vertical.

 

Can i know how do i reset it to straight link by default? 

P.S I can set the links to straight link manually after i drew a curved link but that would be a bit waste of time. I want a straight link by default.

 

Many thanks

Mike Planner

Negative Values For Task Allocations (Cost / Income)

Hi All,

 

Does anyone know if it's possible to have a negative value against a income / cost?

 

Reason for wanting to do this, is that I have an a highway maintenance contract where the client has given us anticipated spends against a list of tasks, but the actual spend was less. Rather than go through and adjust all the anticiapted spends, I was hoping to insert a new task with a negative value against it which represented the sum of the underspend.

 

Kind Regards,

 

Chris

 

Using 2 calendars

Hi Guys

I am using two calendars, one with xmas & bank Holidays, and one with just xmas. The one with xmas + bank holidays is the project calendar and the other is applied to some of the activities. When I apply the second calendar to an activity, the bank holiday stops either side of the bar. Is there a way of making the main calendar go over the activities. I dont need anyone to know I am using 2 calendars its just visual.

 

Many thanks in advance.

 

Andrew

Market Place

No results found... (try selecting a different content filter)

Syndicate content