Top Down Forecast Entry (Manual)

1 reply [Last post]
Adam Garnham
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 3 Oct 2011
Posts: 23
Groups: None

Afternoon All,

Hoping you can help me out please.

I am trying to work out how to manually enter forecast & budget values per month. I am happy with bottom up forecasting but more often than not the clients cost engineer creates a monthly rolling forecast (in Excel) that then needs plugging into project/primavera/asta each month against some high level (often WBS level) bars.

Happy with doing this in everything but Asta, so any wisdom on how this can be achieved in Asta would be fab.

Thanks in advance. Adam.

Replies

Leigh Durnall
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 30 Apr 2010
Posts: 3
Groups: None

You can copy/paste a region of cells between Excel and Asta spreadsheets. Filter out Summary or Expanded tasks though as non-editable values will cause a paste to fail.

Leigh @ Asta