Asta - Draw curve if vertical

1 reply [Last post]
Mike planner
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 3 Feb 2011
Posts: 46
Groups: None

Hello All,

 

Hope you all had a great and rested weekend. A programme has been set to draw curve if vertical by default so everytime i draw a link between 2 tasks, the link will become curve automatically if its vertical.

 

Can i know how do i reset it to straight link by default? 

P.S I can set the links to straight link manually after i drew a curved link but that would be a bit waste of time. I want a straight link by default.

 

Many thanks

Mike Planner

Replies

Mike Testro
User offline. Last seen 44 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Mike

This is in two stages.

First go to Tools > Default > Link and untick the draw curved box.

Second select a link and then Ctrl A to highlight every link

Right click any link and choose Properties and untick draw curved.

Best regards

Mike Testro