Help on drawing bars

2 replies [Last post]
Christine P
User offline. Last seen 10 years 49 weeks ago. Offline
Joined: 27 Apr 2009
Posts: 42
Groups: None
Please can someone help?

I am having trouble trying to draw bars the length I want them. I have a worksheet set up with the following in the date zone area Month, Day (1-31) and Time (Hours mins).

I am trying to make a bar go from 11:00 - 13:30 but will only let me do it either 11:00-13:00 or 11:00-14:00, it wont let me do it half way.

How do i draw a bar with half hours on them please?

Replies

Mike Testro
User offline. Last seen 43 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Christina

As Paul wrote you do need to set the programme time units to minutes to get the results that you require - there is usually a drop down menu on the "Standard" icon menu.

Also make sure that the work pattern in your callendar does not have any Non-Work periods in the time zone that you are looking at.

Finally make sure that any resources attached to the task have the same calendar - this can be done in the modelling dialogue by ticking the "Calendar as Task" box.

There will be a full description of how to apply these items in the Help directory.

Best regards

Mike Testro
Paul Harris
User offline. Last seen 8 weeks 3 days ago. Offline
Joined: 11 Apr 2001
Posts: 618
You need to change your snap Options. Do a search in help for snap and it will tell you all about it.

Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.primavera.com.au