Drop line and Bar Colours

D
Damian Ryan 👤 Member for 20 years 4 months
D
Daya Sugunasingha 👤 Member for 24 years 3 months

Damian

First you will have to create a progress report date or data date.

Open the “Library Explorer”.

Click on the “Progress Period” Folder.

Enter the date you want the Progress Drop Line.

Close the “Library Explorer” window and return to the bar chart.

Go to “Format Bar Chart” and the “Progress” sub-folder and click on the progress date you want to show on the bar chart and close that window and return to the bar chart.

Enter the progress as % or time.

This can be done in a number of ways i.e. click drag on the bar whilst in progress mode, or enter the progress in the progress column on the chart spread sheet column or the Bar / Task Properties.

I hope that this reply is not too late for you.

Regards

Daya

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts