Formatting of bars over non-working time
Forum Sponsor
Top Posters
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Hi All
This is a problem with power project - you can only set non work folding against 1 calendar.
If I have multiple calendars I usually set the folding option to -None-.
By the way any curing time should be set on a 24hr 7day week calendar not just a 7day working week. Set the duration column to ed.
Best regards
Mike Testro
you can also right click on the Format Bar Chart and choose the calendar background for multiple calendars (i.e. 7 days for concrete curing and 5 day working for normal activities)
Thanks fot your help Gijs.
You were right, the problem was with the working pattern. There was a wrong work pattern assigned to the calendar. As soon as I set the right one, the formatting of the bars updated to what I wanted.
Thanks again!
Hi Laurie,
I dont know if I understoof you correct.
But if you set the workpattern in your 7 days calendar there is no weekend exception so to my knowledge there wil be no weekend appearance on your barchart.
If you apply te 7 day calendar to the task.
I tried this and the 5 day calender tasks show the weekend and the 7 day calender shows no weekend.
I hope I understood you correct and have been of any help.