Non-working not shown on Summary Item Line

1 reply [Last post]
Tom Bowles
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 15 Apr 2019
Posts: 2
Groups: None

Hi All,

I am hoping to find a solution that displays the Non-working time shading over the task bars. I am able to format the shading over my whole programme but for some reason it 'disappears' over one particular line (68), and then reappears further down the programme. What is going on?

See image attached to better explain what I am trying to word.

Initially, my thoughts stemmed around different calendars being used, or that it was because the particular line was a 'Summary' but adjusting these seems to make no difference.

I would appreciate any help. Thank you.

Tom

Replies

Mike Testro
User offline. Last seen 35 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Tom

Welcome to planning plannet.

You are showing a different calendar on the summery bar - you can only have one.

When you add a different calendar the sytem asks if you want to switch the display - you declined.

The tasks underneath will have the correct shading.

Best regards

Mike Testro