Show duplicate items for multiple assignments in PP10

Hello,

Asta Powerlines April 2012 (http://www.astadev.com/asta-powerlines-april-2012/asta-powerproject-hints-tips-april-2012/) features an instruction on how to sort your multiple assigned library codes. Step 2 of 'Sorting where multiple codes are assigned' shows an option to 'Show duplicate items for multiple assignments'.

I use PowerProject 10 and it's interface differs from the one of the version used in the instruction. In PowerProject 10 I can't find the option to 'Show duplicate items for multiple assignments'. Is this option not available in this version?

M
Mike Testro 👤 Member for 20 years 5 months

Hi Hans

It is good practice to prefix the text in a library description with a series of leading zero numerics.

They work as text but look like numbers so category 1 would have:

01 Main Text Heading

001 Sub Text Heading

0001 Description.

0002 Description

Pretty much the same as a WBS system.

The advantage of this method is that each description carries with it its place in the heirarchy.

You can also allocate library items into seperate subjects and sub subjects which does the same as the above but without the indication in the description.

Best regards

Mike Testro.

H
Hans van Leeuwen 👤 Member for 13 years 2 months

Hello Mike,

Thanks for confirming that this feature is missing in PP10. Does anybody know a workaround for mimicking this duplication feature in PP10?

 

Best regards,

Hans van Leeuwen

M
Mike Testro 👤 Member for 20 years 5 months

Hi Hans

The instruction is probably written for v 12 and it was not an option in v 10.

Best regards

Mike Testro

Forum Sponsor

Top Posters

MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts