Planner

Planner, Air Products, China, Petrochemical Complex Plant in Chengdu, Sichuan

START Date: 
October, 2009
END Date: 
December, 2010

Master Scheudle development and maintain, regular schedule review meeting, progress reports, trend analysis

Planner, Projacs International, LRT

START Date: 
February, 2009
END Date: 
March, 2010

Current Role

As a planner contributed myself in Project Management Teamapplying knowledge, skills, tools, and techniques to project activities as per project requirement

Planner, Rockwater, (various projects)

START Date: 
August, 1993
END Date: 
March, 1995

Project planner for various internal/ external Projects, including launch and recovery systems, pipeline bundles, umbilical installation

Planner, Macmahon Construction Pty. Ltd., Bulk Earthworks

START Date: 
July, 2009
END Date: 
April, 2013

I am working as a Planner since Jan-07. Worked 2 years in Qatar with piling contracting company. Currently I am working in Australia with one of the leading Construction company in estimation team as a Planner.

Planner, Coogee Resources, Montarra

START Date: 
September, 2006
END Date: 
January, 2007

Project Planner/ Cost Controller for a small field development on the Coogee Resources Montarra development

Planner, Inpex, Ichthys Project

START Date: 
January, 2007
END Date: 
January, 2008

Project planner responsible for the development of the offshore component of the overall Project schedule

Planner, WorleyParsons, NR2 Detail Design

START Date: 
April, 2008
END Date: 
July, 2009

Lead Planner for a nine person (peak) planning team on the detail design and procurement phase for a large new build gas platform

Planner, Skanska, Buildings

START Date: 
January, 2008
END Date: 
April, 2013
  • Development of master schedule to reflect the correct scope of work
  • Monitor progress, compute variance, update schedules and suggest remedial  actions
  • Conduct regular meetings (weekly & monthly) & generate regular look-ahead plans including daily, weekly and two week look-ahead schedule in line with baseline schedule & stringent follow-up with construction managers and subcontractors regarding the hold points & areas of concerns to mitigate all issues
  • Critical path analysis & Generate S curves
  • Preparation of progress report (week

Planner, Thales, Rail Signalling Projects

START Date: 
June, 2006
END Date: 
December, 2006

Project Description

Numerous bids and projects relating to telecoms for the UK rail industry.

Roles and Responsibilities

Part of two-man team responsible for planning & control of all projects in southern Britain, including Earned Value reporting, tracking actual spend at detailed activity level, and resource utilisation forecasts to inform strategic manpower decisions.

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
500

Planner, Thomas Vale Construction, All Housing Division Projects

START Date: 
December, 2008

Tender & Construction Planning,  I am currently working as the sole planning in the Housing New Build Division working on all the incoming Tenders to adjudication and preparation of all Construction Programmes.  Our area of works include Care/Extra Care Accommodation building, Various Housing Schemes mainly in the Social Sector, I provide a varying amount of planning input to the live projects, I monitor progress to all live projects weekly also produce Collaborative/Target Programmes and other programmes as required through the duration of projects.