Senior Planner, ELB Engineering, Medupi Coal Fired Power Station – South Africa

START Date: 
April, 2010
END Date: 
April, 2011

Developed the EPC Master Project Schedule for the engineering & procurement & construction phase of the project. (LSTK Lump Sum Turnkey Project)

My responsibilities were to ensure that the Project Team and Manager are aware of the current status and critical issues on the project. Management of the other project Planner working on site.

Integration of contractors schedules into the overall project schedule.

Evaluate the Contractors progress and report back

Update the schedule on a weekly basis, including setting up of the S-Curves.

Project Planner (SIB Projects For Anglo American), Sightfull - Anglo American, SIB Projects For Anglo American - Platinum, Amandelbult Section

START Date: 
June, 2011
END Date: 
November, 2012

Herewith some of the basic tasks I’ve done at the above mentioned company:

  • Attending Tender Meetings (To get information for tender program-schedule)
  • Design Tender Program-Schedule (With minimum detail –baseline program /schedule Level 1-2)
  • Attending Tender Award Meeting (To get information for more detail program/schedule Level 2-3)
  • Attending Site Meeting (To see site layout and getting the final detail )
  • Project Starts Visit Site (Start design a Construction program/schedule level 4-5)
  •  Attending Site M

Project Planner, Louwill Engineering/ Power Steel Construction, Steel Construction -Fabrication Of Steel, Erecting Of Steel , Building Of Headgears, Winder Houses , Re- Building Headgears

START Date: 
October, 2010
END Date: 
May, 2011

 

Project Planner  PowerSteel Constuction (2010/10/24 - 2011/05/31)

 

 Herewith some of the basic tasks I’ve done at the above mentioned company:

  • Attending Tender Meetings (To get information for tender program-schedule)
  • Design A Tender Program-Schedule (With minimum detail –baseline program /schedule Level 1-2)
  • Attending Tender Award Meeting (To get information for more detail program/schedule Level 2-3)
  • Attending Site Meeting (To see site layout and getting t

Project Planner, Louwill Engineering/ Power Steel Construction, Steel Construction -Fabrication Of Steel, Erecting Of Steel , Building Of Headgears, Winder Houses , Re- Building Headgears

START Date: 
October, 2010
END Date: 
May, 2011

 

Project Planner  PowerSteel Constuction (2010/10/24 - 2011/05/31)

 

 Herewith some of the basic tasks I’ve done at the above mentioned company:

  • Attending Tender Meetings (To get information for tender program-schedule)
  • Design A Tender Program-Schedule (With minimum detail –baseline program /schedule Level 1-2)
  • Attending Tender Award Meeting (To get information for more detail program/schedule Level 2-3)
  • Attending Site Meeting (To see site layout and getting t

Deputy Project Manager-Planning, Simplex Infrastructures Limited, The World Towers

START Date: 
May, 2012
END Date: 
September, 2015

Worked as Depuety Project Manage- Planning for Simplex Infrastructures Limited. Mumbai for esteemed 'King Tower' project.

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1000

Project Planner, Masters Splice & Termination, Koepe Winder Electrical Installation, Central Balsting System Installations, Re - Building Mining Shafts(Electrical), Switch Gear , Substations

START Date: 
August, 2009
END Date: 
September, 2010

Project Planner  Master Splice & Termination (2009/08/11 - 2010/09/31)

 

 Herewith some of the basic tasks I’ve done at the above mentioned company:

  • Attending Tender Meetings (To get information for tender program-schedule)
  • Design A Tender Program-Schedule (With minimum detail –baseline program /schedule Level 1-2)
  • Attending Tender Award Meeting (To get information for more detail program/schedule Level 2-3)
  • Attending Site Meeting (To see site layout and getting the fin

Junoir Project Planner, B&W Instrumentation And Electrical, Coal Refinery Plant, Crusher Plant, Workshops. I was responsible for more than 15 Projects small and major

START Date: 
January, 2008
END Date: 
March, 2009

Planner  B&W Instrumentation and Electrical Limited (2008/01/25 – 2009/03/01)

 

Herewith some of the basic tasks I’ve done at the above mentioned company:

  • Attending Tender Meetings (To get information for tender program-schedule)
  • Design A Tender Program-Schedule (With minimum detail –baseline program /schedule Level 1-2)
  • Attending Tender Award Meeting (To get information for more detail program/schedule Level 2-3)
  • Attending Site Meeting (To see site layout and getting the fi

Junoir Project Planner, B&W Instrumentation And Electrical, Coal Refinery Plant, Crusher Plant, Workshops. I was responsible for more than 15 Projects small and major

START Date: 
January, 2008
END Date: 
March, 2009

Planner  B&W Instrumentation and Electrical Limited (2008/01/25 – 2009/03/01)

 

Herewith some of the basic tasks I’ve done at the above mentioned company:

  • Attending Tender Meetings (To get information for tender program-schedule)
  • Design A Tender Program-Schedule (With minimum detail –baseline program /schedule Level 1-2)
  • Attending Tender Award Meeting (To get information for more detail program/schedule Level 2-3)
  • Attending Site Meeting (To see site layout and getting the fi

Planning Manager, Intermass Engineering & Contracting, buildings, Hotels, Schools, hospitals

START Date: 
October, 1997
END Date: 
June, 2013
  • Represent the Company in planning related meetings with Clients
  • Leading meetings with subcontractors, site managers, planning engineers to coordinate subcontract schedule and day-to-day operations.
  • Provide supervision and assistance to planners in the development and integration of individual schedules into the total project plan.
  • Produce the weekly reports and coordinating input from site managers.

PLANNING ENGINEER, HBK Contracting WLL, Heart of Doha land Building

START Date: 
June, 2007

·         Tender & Detail  Planning using Primavera (P6).(Clause 14 Programme)

·         Preparation Programme Qty & Cost Uploading Primavera Software (P6).

·         Project scheduling to submit and approve Client.