A Delay Reason can be because of:
. 1-Activity: driving predecessor, logic link
. 2-Resource availability
. 3-Calendar Exception: exception taking over any other reason, say an activity cannot work on month 3 but it is scheduled for month 1 because of predecessor logic, if predecessor delays it to start on month 3 it will be further delayed to start on month 4.
. 4-Financial
. 5-Retained Logic or Broken Link
I know I can filter activities for reasons 1, 2 and 5, but how for 3 and 4. I believe all the above reasons should be shown on the Delay Reason column, but until then, what work around are feasible for the creation of my activities filter (reasons 3 and 4)?
By adding a filter for critical activities I will get it filtered further down to all the delay reasons along the critical path for critical path analysis.

Best regards,
Rafael
Replies