GUILD News Flash | Bringing recognition to the Project Controls Profession

Primavera P6 R7.0.0 Duration Request (showing instead of Original working duration the real calendar duration)

14 replies [Last post]
Adnan Kocak
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 8 Apr 2004
Points: 11

Hello,

I have a question: If somebody helps me I will be appriciated.

Sample:

Activity Start Date: 31 August 2012 

Activity Finish Date: 25 February 2013

The Primavera defined duration from the defined calendar is showing me: 145 days.

but the real calendar duration from the start date to finish date is: 179 days.

In P6 our Employer's request is to show on the schedule the real duation instead of working duration. Also in the summary of the work schedule is showing in total 750 days instead of 912 days.

Is it possible to show the real calendar duration (total days) in the summaries of the work schedule.

I will be happy, if somebody from the friends here can help me, if they had before some request like that in the past.

 

Thank you very much.

Replies

Kaif Mohsin
User offline. Last seen 1 day 14 hours ago. Offline
Joined: 15 Feb 2011
Points: 11
Groups: None

Dear Adnan,

In P6 Rel 7, the duration for the summary at WBS level is calculated in the following two ways:

1. If all the activities lying under a WBS follow the same calendar then the duration at the summary level is calculated based upon that calendar only.

2. If the activities lying under a WBS have different calendars assigned to them then the duration at the summary level is calculated based upon the Project's Default calendar (the one that is assigned under the Defaults tab of the Project window).

So, the only solution possible to your query is the same as suggested by Mr. Raymund before that is to create a dummy activity for every WBS and set its activity calendar as 7 days. Then mark the 7 days calendar as the Project's default calendar under the Defaults tab of the Project window.

Regards,

Kaif

Kaif Mohsin
User offline. Last seen 1 day 14 hours ago. Offline
Joined: 15 Feb 2011
Points: 11
Groups: None

Dear Adnan,

In P6 Rel 7, the duration for the summary at WBS level is calculated in the following two ways:

1. If all the activities lying under a WBS follow the same calendar then the duration at the summary level is calculated based upon that calendar only.

2. If the activities lying under a WBS have more than one calendar assigned to them then the duration at the summary level is calculated based upon the Project's Default calendar (the one that is assigned under the Defaults tab of the Project window).

So, the only solution possible to your query is the same as suggested by Mr. Raymund before that is to create a dummy activity for every WBS and set its activity calendar as 7 days. Then mark the 7 days calendar as the Project's default calendar under the Defaults tab of the Project window.

Regards,

Kaif

Adnan Kocak
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 8 Apr 2004
Points: 11

Raymund,

Thank you very much for your supoort. But still the durations are showing only the working days durations. Also by total project, if you filter the critical activities and hide in "group and sort" the emtpy summaries ("hide if empty") , the duration is showing only the working duration days.

 

regards

Raymund de Laza
User offline. Last seen 7 hours 32 min ago. Offline

Adnan,

All Calendars are intact.... it will not be affected by making the 7 days calendar as default.

It will just show what's your requirement is.

 

Adnan Kocak
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 8 Apr 2004
Points: 11

Hi Raymund,

 

Sorry for my late response. If I make a default calendar with 7 days working day. What will be happen with the calendar what we have created with religious and holidays nonworking days ?

 

Adnan Kocak
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 8 Apr 2004
Points: 11

Hi Raymund,

 

Sorry for my late response. If I make a default calendar with 7 days working day. What will be happen with the calendar what we have created with religious and holidays nonworking days ?

 

Raymund de Laza
User offline. Last seen 7 hours 32 min ago. Offline

Try creating a calendar with 7 days and make as the default calendar.... even witout adding a dummy activities...

Adnan Kocak
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 8 Apr 2004
Points: 11

Hi Raymund,

 

Thank you for your response. But to give in a big schedule for every WBS code a dummy activity is not easy. Under every group will be an empty activity. I hope my friends can find another solution in our forum.

 

Thank you again.


Adnan

Adnan Kocak
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 8 Apr 2004
Points: 11

Hi Raymund,

 

Thank you for your response. But to give in a big schedule for every WBS code a dummy activity is not easy. Under every group will be an empty activity. I hope my friends can find another solution in our forum.

 

Thank you again.


Adnan

Raymund de Laza
User offline. Last seen 7 hours 32 min ago. Offline

Hi,

Create a dummy activity for every WBS and set its activity calendar as 7 days.

Then mark the 7 days calendar as the default calendar and you get what you requires.

 

Adnan Kocak
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 8 Apr 2004
Points: 11

Of course it's it will work with 7 days calendar. But we are working 6 days in a week. Also we have put the religious and holidays in the calendar as nonworking days. ıs there really no solution for this problem. Please help me.

 

Thank You..

Adnan Kocak
User offline. Last seen 38 weeks 4 days ago. Offline
Joined: 8 Apr 2004
Points: 11

Of course it's it will work with 7 days calendar. But we are working 6 days in a week. Also we have put the religious and holidays in the calendar as nonworking days. ıs there really no solution for this problem. Please help me.

 

Thank You..

Anoon Iimos
User offline. Last seen 25 weeks 6 days ago. Offline
Joined: 22 Sep 2006
Points: 1169

try creating a 7 days per week calendar and use it; I guess this will solve your problem

David Kelly
User offline. Last seen 24 weeks 2 days ago. Offline
Joined: 19 Oct 2004
Points: 370

Adnan,

 

Every one of us has wanted this for 10 years.  No one is listening

Market Place

A user guide and training manual written for professionals who wish to learn how to plan and control projects in an established Primavera Enterprise environment with or without Resources & Roles.
The book is designed for users of earlier versions to upgrade their skills and for new planners to learn the software.
We want to build software that solves real problems, allow people to work more productive and happier.
The toolkit provides advanced analytical tools which can help identify areas of poor schedule quality at the click of a button.
EVA18 is the major UK event for Project Control knowledge, know-how and networking. EVA is a conference organised by a project management practitioner for project practitioners and stakeholders