Primavera P6 R7.0.0 Duration Request (showing instead of Original working duration the real calendar duration)
Hello,
I have a question: If somebody helps me I will be appriciated.
Sample:
Activity Start Date: 31 August 2012
Activity Finish Date: 25 February 2013
The Primavera defined duration from the defined calendar is showing me: 145 days.
but the real calendar duration from the start date to finish date is: 179 days.
In P6 our Employer's request is to show on the schedule the real duation instead of working duration. Also in the summary of the work schedule is showing in total 750 days instead of 912 days.
Is it possible to show the real calendar duration (total days) in the summaries of the work schedule.
I will be happy, if somebody from the friends here can help me, if they had before some request like that in the past.
Thank you very much.
Dear Adnan,
In P6 Rel 7, the duration for the summary at WBS level is calculated in the following two ways:
1. If all the activities lying under a WBS follow the same calendar then the duration at the summary level is calculated based upon that calendar only.
2. If the activities lying under a WBS have different calendars assigned to them then the duration at the summary level is calculated based upon the Project's Default calendar (the one that is assigned under the Defaults tab of the Project window).
So, the only solution possible to your query is the same as suggested by Mr. Raymund before that is to create a dummy activity for every WBS and set its activity calendar as 7 days. Then mark the 7 days calendar as the Project's default calendar under the Defaults tab of the Project window.
Regards,
Kaif
Dear Adnan,
In P6 Rel 7, the duration for the summary at WBS level is calculated in the following two ways:
1. If all the activities lying under a WBS follow the same calendar then the duration at the summary level is calculated based upon that calendar only.
2. If the activities lying under a WBS have more than one calendar assigned to them then the duration at the summary level is calculated based upon the Project's Default calendar (the one that is assigned under the Defaults tab of the Project window).
So, the only solution possible to your query is the same as suggested by Mr. Raymund before that is to create a dummy activity for every WBS and set its activity calendar as 7 days. Then mark the 7 days calendar as the Project's default calendar under the Defaults tab of the Project window.
Regards,
Kaif
Raymund,
Thank you very much for your supoort. But still the durations are showing only the working days durations. Also by total project, if you filter the critical activities and hide in "group and sort" the emtpy summaries ("hide if empty") , the duration is showing only the working duration days.
regards
Adnan,
All Calendars are intact.... it will not be affected by making the 7 days calendar as default.
It will just show what's your requirement is.
Hi Raymund,
Sorry for my late response. If I make a default calendar with 7 days working day. What will be happen with the calendar what we have created with religious and holidays nonworking days ?
Hi Raymund,
Sorry for my late response. If I make a default calendar with 7 days working day. What will be happen with the calendar what we have created with religious and holidays nonworking days ?
Try creating a calendar with 7 days and make as the default calendar.... even witout adding a dummy activities...
Hi Raymund,
Thank you for your response. But to give in a big schedule for every WBS code a dummy activity is not easy. Under every group will be an empty activity. I hope my friends can find another solution in our forum.
Thank you again.
Adnan
Hi Raymund,
Thank you for your response. But to give in a big schedule for every WBS code a dummy activity is not easy. Under every group will be an empty activity. I hope my friends can find another solution in our forum.
Thank you again.
Adnan
Hi,
Create a dummy activity for every WBS and set its activity calendar as 7 days.
Then mark the 7 days calendar as the default calendar and you get what you requires.
Of course it's it will work with 7 days calendar. But we are working 6 days in a week. Also we have put the religious and holidays in the calendar as nonworking days. ıs there really no solution for this problem. Please help me.
Thank You..
Of course it's it will work with 7 days calendar. But we are working 6 days in a week. Also we have put the religious and holidays in the calendar as nonworking days. ıs there really no solution for this problem. Please help me.
Thank You..
try creating a 7 days per week calendar and use it; I guess this will solve your problem
Adnan,
Every one of us has wanted this for 10 years. No one is listening
Replies