Hello,
I have a question: If somebody helps me I will be appriciated.
Sample:
Activity Start Date: 31 August 2012
Activity Finish Date: 25 February 2013
The Primavera defined duration from the defined calendar is showing me: 145 days.
but the real calendar duration from the start date to finish date is: 179 days.
In P6 our Employer's request is to show on the schedule the real duation instead of working duration. Also in the summary of the work schedule is showing in total 750 days instead of 912 days.
Is it possible to show the real calendar duration (total days) in the summaries of the work schedule.
I will be happy, if somebody from the friends here can help me, if they had before some request like that in the past.
Thank you very much.