Original Duration vs Remaining Duration
Forum Sponsor
Top Posters
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
Soheil Barekat
4 posts
Kari,
It is a setting in P6. Project Window-> Calculation tab-> Activities. Tick Link Budget and At Completion for not started Activities and select Reset Remaining Duration and Units to Original if you wanted to synchronize OD and RD. Select Reset Original Duration and Unit to Remaining if you want to maintain remaining duration when progress actual has been remove to activity.