Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Price/ Unit - Budget Cost

7 replies [Last post]
Haresh Jayanth
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Primavera is calculating Budgeted Cost by following equation , w.r.t Price / Unit.
For example:

a) Price / Unit: $120 /d
b) Suppose Duration of the activity is 10 days.
c) Budgeted cost is shown as $ 150 instead of $ 1200, which means primavera is calculating Budget cost based on the following formula i.e.

(120 / 8) (No of working hours in a day) * 10 (duration)= $150.

But it take this formula: 120 * 10days = $1200, why this is happening??? Kindly advice.....

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

view show on bottom resource usage profile 

then click the cost box 

Russ Tomb
User offline. Last seen 4 years 10 weeks ago. Offline
Joined: 10 Feb 2020
Posts: 11
Groups: None

Hi! I am newbie with this type of program and career line.

 

Please enlighten me with resources. They gave me a file with indicated budget for each activity and I need to make an s-curve using p6.

 

Is this possible?

 

Ex.

Activity ID Activity Name Orig Duration Start Finish   

   A1020     Excavation            180 05-Jan-19 03-Jul-19
Rodel Marasigan
User offline. Last seen 2 days 50 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
This is common if you modify your resource rate or change something which is also affected by duration type setting. If both prices assigned to resource and activity detail, resource tab are the same then try this.
Tools-> Recalculate assigment Cost. That should fixed the problem.

Note: Things that needs to check
1) Edit-> User Preferences-> Time Units tab-> Unit Format (is it hour or day?)
2) Resource max unit/time = (8/day or 10/day)
3) Resource Price/ Unit = ($?/h or $?/d)
4) Activity Window-> Resource tab-> Budget Unit = ?
5) Activity Window-> Resource tab-> Price/unit = ($?/h or $?/d)
Irfan Khan
User offline. Last seen 11 weeks 3 days ago. Offline
Joined: 19 Jul 2009
Posts: 138
Hi,

Joel is correct refresh ur data or check ur Admin Preferences may be something wrong there......!

regards,,,,,

Joel Villanueva
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 21
Haresh,

Anyway, just try to re-schedule and refresh data sometimes it displays wrong output if you did some editing of data without refreshing and or re-scheduling.

Regards,
Joel
Haresh Jayanth
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Dear Mr. Joel,

Both prices assigned to resource and activity detail, resource tab are the same.

But still the problem persists

regards,

Haresh
Joel Villanueva
User offline. Last seen 12 years 7 weeks ago. Offline
Joined: 7 Mar 2010
Posts: 21
Hi Haresh,

Check if your price/unit under “Activity details” resources column is the same with your price/unit assigned under “Resources window” if not, re-schedule the program and click refresh data under “File menu”.

Regards,
Joel