Primavera is calculating Budgeted Cost by following equation , w.r.t Price / Unit.
For example:
a) Price / Unit: $120 /d
b) Suppose Duration of the activity is 10 days.
c) Budgeted cost is shown as $ 150 instead of $ 1200, which means primavera is calculating Budget cost based on the following formula i.e.
(120 / 8) (No of working hours in a day) * 10 (duration)= $150.
But it take this formula: 120 * 10days = $1200, why this is happening??? Kindly advice.....
For example:
a) Price / Unit: $120 /d
b) Suppose Duration of the activity is 10 days.
c) Budgeted cost is shown as $ 150 instead of $ 1200, which means primavera is calculating Budget cost based on the following formula i.e.
(120 / 8) (No of working hours in a day) * 10 (duration)= $150.
But it take this formula: 120 * 10days = $1200, why this is happening??? Kindly advice.....