Man power Productivity

13 replies [Last post]
Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

Dear Friends

It will be highly appreciated if you will be clearing my doubt ASAP.

Eg .I have a task of block work of Quantity  400 M2 .

Kindly clarify the production in the attached picture .

2.5 M2 per Hour means it is the production rate of one mason ???/Thn what is the propotion of helper .Kindly  give me the global propotion of Labour with the masons (block,plaster,shuttering,Steel fixing what ever).And also Please compute me the Block mason with the helper for the above quantity....

Regards

Arun

643
block_work.jpg

Replies

Gary Whitehead
User offline. Last seen 4 years 47 weeks ago. Offline

Dear All:

If anyone wants the productivity info from Arun, please send him a private message with your email ID (click on the little envelope next to his name).

I'm locking this thread before it becomes full of begging letters.

Dura Cell
User offline. Last seen 2 years 41 weeks ago. Offline
Joined: 7 Dec 2010
Posts: 32

 

Dear Mr.Arun,

Please send me a copy as well my email is d.cell@yahoo.com

Thanks in advance

Dura

Dura Cell
User offline. Last seen 2 years 41 weeks ago. Offline
Joined: 7 Dec 2010
Posts: 32

 

Dear Mr.Arun,

Please send me a copy as well my email is d.cell@yahoo.com

Thanks in advance

Dura

shaik yakub
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 25 Jul 2007
Posts: 12

HI Arun

 

Can u plz send me a copy to yakub_sky@yahoo.co.in or yakub.sky@gmail.com

 

Thanks in advance,

 

Regards,

Shaik

shaik yakub
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 25 Jul 2007
Posts: 12

Hi can u plz send me a copy on yakub_sky@yahoo.co.in or yakub.sky@gmail.com

 

thanks in advance

Regards,
Shaik

Justin James
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 19 Aug 2009
Posts: 32
Groups: GPC Qatar, TILOS

Hello Mr.Arun,

Can i have a copy as well my mail is sjustinjames@gmail.com

Thanks & Regards

Justin

Edison
User offline. Last seen 12 years 32 weeks ago. Offline
Joined: 18 Sep 2010
Posts: 2
Groups: None

Dear Mr. Arun,

Please send me the productivity rates at use private message service

Regards,

Owais

Rafael Davila
User offline. Last seen 17 hours 24 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

http://www.escsi.org/uploadedFiles/Technical_Docs/SmartWall_Masonry/3700...

Without drawings and specifications you cannot make a good estimate, it is not the same for different block size, not the same production rate for blocks to be installed on the ground than for blocks to be installed using scaffolding. Also the vertical and horizontal reinforcement matter. That is why most companies do not outsource scheduling unless the specifications call for a scheduling software they do not know. It is a pity industry have not realized that scheduling should be done in-house, by the team that will be in charge of the means and methods. We have some specifications that even require the contractor to hire an external scheduler to use their particular software choice, unbelievable but true.

Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

Dear Friends

 

I got the Productivity rate from a Engineer who  is silent the Forum (Mr.Pinan).

Iam very thankful to Mr.Pinan.

If any body wants  the productivity with Crew Please post their email ID...

This productivity we can use for  GCC Only....

 

Regards

Arun  

Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar

 

 

Dear Friends

Iam Supporting Nidan...

We planners have to prepare a production rate based on the manpower using..

for eg 1000 m2 block work 

10 Block builders its propotion of helpers..

If any body have please share...

 

Arun

Nanding D.
User offline. Last seen 12 years 31 weeks ago. Offline
Joined: 19 Dec 2010
Posts: 17
Groups: None
Hi Planners, Production rate in Planning Planet is great, but I think it will be more meaningful if the Production Rate will be associated with basic Crew Description and Equipment Detail. Thanks, Nanding
Mike Testro
User offline. Last seen 6 weeks 2 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Arun

The most precise way to get production rates for your project is to look at the tender breakdown.

The individual rates should be set at Labour - Plant - Material.

The money can be converted to hours using the labour rate per hour.

If there is no individual labour rate then apply a reasonable labour percentage - 35% to 40% for blockwork

You should also take account of the other items related to blockwork productivity:

Openings and lintels

Angle head restraints

M&E Openings

Fire Proofing etc.

These should all be added to the blockwork hours and then allocated pro rata to your programme tasks.

Best regards

Mike Testro

Rafael Davila
User offline. Last seen 17 hours 24 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

m2/mr means some production rate per hour for a crew that can be a mason plus a helper

m2/m-hr would be production rate per man-hour

Production rates without crew description are misleading, even per man-hour, you might have several production rates depending on the crew composition. It is not the same moving dirt with a 10-cm truck than with a 20-cm truck for one hour or one man-hour. It is not the same placing concrete with a wheelbarrow than with a 90-cm per hour concrete pump that can swallow several concrete trucks in an hour with ease, two chutes side by side so there is no waiting between trucks.