Hi -Experts,
We got (awarded) one project that is Chemical Plant Project size is small .project duration is 13 Months,
Project manager asking me to prepare a L3 schedule while i do not have enough information to do so,
information like Procurement , duration (vendor delivery time) for project Equipment and material, Nos of Engineering Drawings, for Process,Civil , mach,
i have only Bid Schedule which is Master Schedule with overall duration for EPC.
I know Plot plan of the Project under preparation , client has issue only ref.p & IDs , while i ask to discipline Engineers to provide me information for L3 schedule, they said we need couple of days to estimate the nos of Drawings and Docs,
My Project manager pushing me hard to finalize the schedule, i never work before with this kind of PM.
Please let me know what is the way to prepare a L3 schedule with out detail information for PM as well as Client.
How i can reply to project manager, even he is aware of all situation.
Please Help me with your wide experience,
Thanks in advance and best regards
Replies