how many manhour,weight factor, wbs level 1 to 5
Forum Sponsor
Top Posters
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
The formulas are applied to total assignments but can be extended to relative %complete same as if weight factor equals 1.
I am still scratching my head to understand what it means.
If your software does not allows you to group resources by activity on the Gantt chart then Monkey will not be able to help you, the weight factor assigned to monkey hours is zero.
EPRM DBSQL Execution failure in module PM.exe at 00117558PRM DBA Access error: DAta base servor error;
Its not allowing me to copy/ delete projects or activities
it says primavera file group is full . ask to create disk space ; how can we increase disk space