Tips on using this forum..
(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?
(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.
how many manhour,weight factor, wbs level 1 to 5
please help me??!!
please submite with this address: soroosh_anbaei@yahoo.com
The formulas are applied to total assignments but can be extended to relative %complete same as if weight factor equals 1.
I am still scratching my head to understand what it means.
If your software does not allows you to group resources by activity on the Gantt chart then Monkey will not be able to help you, the weight factor assigned to monkey hours is zero.
Replies