Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

%26 project planning 2)primavera p6 3)Reports

Assistant Planner & Scheduler, Dantata & Sawoe Construction (Nig) Ltd., & Oil & Gas Projects 2) Buildings 3) Infrastructurus

START Date: 
October, 2015

Getting actual start and actual finish of activities. updating it on P6. estimation of quantities and manpower for works

Experience Hours (Planning & Scheduling): 
350
Experience Hours (Cost Management): 
150

Assistant Planner & Scheduler, Dantata & Sawoe Construction (Nig) Ltd., & Oil & Gas Projects 2) Buildings 3) Infrastructurus

START Date: 
October, 2015

Getting actual start and actual finish of activities. updating it on P6. estimation of quantities and manpower for works

Experience Hours (Planning & Scheduling): 
350
Experience Hours (Cost Management): 
150

Project Planner, Network Rail, (various projects)

START Date: 
September, 2005
END Date: 
February, 2007

Creating and monitoring plans for projects in the North West of the UK by Network Rail.  Reviewing contractors plans and feeding back to the project team as required.

Construction Project Controls/Planning Engineer, Laing O'Rouke UK Heathrow T2, Heathrow Airport Terminal 2

START Date: 
April, 2013
END Date: 
November, 2013

Project Controller, part of the PMO team that the programmes for the work streams that are part of the additional changes to the HETCo 1 main project. Cost and resource load and maintain the change programme to enable the final handover of Heathrow Terminal 2A. 

 

Experience Hours (Planning & Scheduling): 
1050
Experience Hours (Cost Management): 
350

ANALYST / PLANNING ENGINEER, Enron, Dabhol LNG Project

START Date: 
July, 1999
END Date: 
October, 2001

Project – Construction of LNG Terminal for 2184MW Dabhol Power Project, Maharashtra

Client – Dabhol Power Company

Project Description – 2184 MW combined cycle power project, LNG receiving terminal and re-gasification facilities of 5MMTPA capacity. Scope involved 3x160,000 M3 LNG Storage Tanks, Marine Terminal and 2 km Jetty with LNG unloading facility, Breakwater construction and re-gasification facilities, OSBL piping for natural gas supply to power block and commercial usage.

Experience Hours (Planning & Scheduling): 
4350

project engineer, sukruuzun , Commercial building

START Date: 
February, 2012

Planning engineer planning and schedule for buildings and towers using primavera P6 and ms project 

Experience Hours (Forensic Analysis): 
6100

Operations and Maintenance Planner/Scheduler, BP, BP Horn Mountain

START Date: 
March, 2006
END Date: 
October, 2012

Daily development of operational, maintenance, and turn around schedules, planning activities, Maximo Super-user, new service & material provider contract negotiation.

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
12000

Lead Planner - Offshore Works, BECHTEL, Hay Point Expansion Phase 3

START Date: 
May, 2011
END Date: 
June, 2014
  • Schedule Management
    • Review sub-contactor network program
    • Identify Logic and duration issues
    • Identify interfaces with other contractors and its impact
    • Identify engineering deliverables issues and its impacts with procurement and construction
    • Identify material delivery issues and its impacts with construction
  • Resource management
    • Review sub-contractor resource plan
    • Identify major issues with resource availability
    • Review sub-contactor's Plant and equipment plan
  • Earned Value mana
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
950
Experience Hours (Forensic Analysis): 
1000

Western Hemisphere Turnaround Manager , BP Americas, Multiple Projects including Production increasing and sustaining initiatives.

START Date: 
October, 2008
Western Hemisphere Turnaround Manager - Managing onshore and offshore production Turnaround and Outage strategy and high complexity events with risk to significant production deferral. - Responsible for events throughout Alaska, Gulf of Mexico, Trinidad.
Experience Hours (Planning & Scheduling): 
20000
Experience Hours (Cost Management): 
15000
Experience Hours (Forensic Analysis): 
8000

Sr. Project Controls Engineer, Shell International, Hazira, Shell LNG Regasification project

START Date: 
March, 2003
END Date: 
December, 2004
  • Schedule Review of Sub-contractor
  • Progress Measurement and Monitoring
  • Higher Management Reporting
  • Risk Assessment and Analysis of the project
  • Conduct weekly, monthly schedule review meeting
  • Progress reports, curves and charts
Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Forensic Analysis): 
400

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content