Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Enron

ANALYST / PLANNING ENGINEER, Enron, Dabhol LNG Project

START Date: 
July, 1999
END Date: 
October, 2001

Project – Construction of LNG Terminal for 2184MW Dabhol Power Project, Maharashtra

Client – Dabhol Power Company

Project Description – 2184 MW combined cycle power project, LNG receiving terminal and re-gasification facilities of 5MMTPA capacity. Scope involved 3x160,000 M3 LNG Storage Tanks, Marine Terminal and 2 km Jetty with LNG unloading facility, Breakwater construction and re-gasification facilities, OSBL piping for natural gas supply to power block and commercial usage.

Experience Hours (Planning & Scheduling): 
4350

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content