Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Schedule Engineer

Schedule Engineer, McCarthy Building Companies, Multiple Projects

START Date: 
January, 2001
END Date: 
February, 2011

Schedule Development

* Develop and evaluate proposal and bid schedules for feasibility and risk analysis.

* Participate in project kickoff and startup meetings.  Function as a facilitator and expeditor throughout the plan and schedule development process.

* Work with the project team to develop the Project Execution Plan and Baseline Schedule, and assist with the creation of the documentation as required to gain approval of Baseline Schedules.

Schedule Engineer, Saudi Aramco thru Al-Jehat Trading, 1) Infrastructure 2) Sewerage Treatment Plant 3) Building works

START Date: 
April, 2015
  • Review and comment on work schedule prepared by the contractor and report findings to Project Engineer.
  • Review and comment on other planning/progress related reports submitted by contractor including progress invoice.
  • Monitor work schedule and status, ensuring progress reported is a true reflection of work achieved and report areas of concern to Project Engineer.
  • Attend any relevant planning meetings with Project Engineer and Contractor.
  • Scrutinize in detail the contractor work schedule in relation to logics, critical paths, floats and lags and make any
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
400

Schedule Engineer, Areva, Nuclear Power Plant, Olkiluoto

START Date: 
August, 2013

-Develop and maintain the Engineering Time Schedule with input from the Engineering project team in Erlangen, Germany and support from the OL3 job site team.

-Use Primavera P6 for the Master Project Schedule and MS Project for various detailed schedules as needed to support the Engineering group and Project needs.

-Organize internal meetings with the relevant project members to update the Engineering Time Schedules and assure interrelationships with other groups are correctly modeled in the schedule.

Experience Hours (Planning & Scheduling): 
3050
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
350

Schedule engineer, GS ENGINEERING & CONSTRUCTION CO, INTER REFINERIES PIPELINE II-PHASE II for TAKREER

START Date: 
February, 2011

The scope of the work include Engineering ,procurement, construction and commissioning and start up for the project.Review current status of both Engineering and Procurement for the Project prepare a revised detailed Level 3 control schedule (Primavera P3) incorporating the physical status and all change orders. This was part of the integrated schedule and network for the EPC contract. Assist the cost engineer in the revised control budget.

schedule engineer, prima, LNG project

START Date: 
June, 2013

LNG project , PTKS Furance  project, Power Plant,  Oil transform pipe project

Schedule Engineer, Catamount Constructors, (various projects)

START Date: 
March, 2012
END Date: 
October, 2013

Southwest Regional Schedule Engineer.  Responsible for development and maintenance of all bid and proposal schedules, construction baseline schedules, and updates.

Schedule Engineer, Saudi Aramco, Mantain Potencial

START Date: 
June, 2011

Senior Schedule Engineer whithin Mantain Potencial.Tasked with Project Controls functions for a large portfolio.

Schedule Engineer, SK Engineer & Construction, Yanbu Export Refinery Project (EPC-2, Crude Package)

START Date: 
March, 2010

Schedule Engineer

Yanbu Export Refinery Project

(EPC-2, Crude Package)

 

Schedule Engineer

Yanbu Export Refinery Project

(EPC-2, Crude Package)

Schedule Engineer, Chiyoda Technip Joint Venture (CTJV), Al Khaleej Gas Phase 2, Ras Laffan

START Date: 
August, 2007
END Date: 
January, 2010

-prepare PMC (pre mechanical check)

-update master construction schedule of Level-III based on the information from supervisor by use of Primavera (P3 /3.1).

-define linkage between construction schedule and commissioning schedule

-CPM analysis using master construction schedule of Level-III

-check subcontractor’s detail construction schedule of Level-IV based on the Level-III schedule.

-review 3 weeks look-ahead schedule submitted by subcontractors.

-loading of man-power and/or progress weighted value to activities on Level-III schedule.

Experience Hours (Planning & Scheduling): 
4800
Experience Hours (Forensic Analysis): 
450

Market Place

No results found... (try selecting a different content filter)

Syndicate content