Scheduling and reporting using Primavera P6

Turnaround Planning Lead, BP AzSPU, Azerbaijan Delivery Unit (BP)

START Date: 
July, 2011

Turnaround Planning Lead for the Azerbaijan Offshore SPu of BP. Delivering all levels of plans and schedules for the delivery of Platform Turnarounds in the Caspian Sea region off Azerbaijan. Developing reporting and monitoring systems to BP International Standards

Schedule Engineer, Chiyoda Technip Joint Venture (CTJV), Al Khaleej Gas Phase 2, Ras Laffan

START Date: 
August, 2007
END Date: 
January, 2010

-prepare PMC (pre mechanical check)

-update master construction schedule of Level-III based on the information from supervisor by use of Primavera (P3 /3.1).

-define linkage between construction schedule and commissioning schedule

-CPM analysis using master construction schedule of Level-III

-check subcontractor’s detail construction schedule of Level-IV based on the Level-III schedule.

-review 3 weeks look-ahead schedule submitted by subcontractors.

-loading of man-power and/or progress weighted value to activities on Level-III schedule.

Experience Hours (Planning & Scheduling): 
4800
Experience Hours (Forensic Analysis): 
450