Schedule Engineer, Areva, Nuclear Power Plant, Olkiluoto

START Date: 
August, 2013

-Develop and maintain the Engineering Time Schedule with input from the Engineering project team in Erlangen, Germany and support from the OL3 job site team.

-Use Primavera P6 for the Master Project Schedule and MS Project for various detailed schedules as needed to support the Engineering group and Project needs.

-Organize internal meetings with the relevant project members to update the Engineering Time Schedules and assure interrelationships with other groups are correctly modeled in the schedule.

-Update the time schedule with actual progress and design sequence development for both AREVA and third party activities.

-Analyze the activities, durations, links, and critical path; inform the managers when variations or delays from the plan are detected; forecast completion dates; and recommend recovery plans to mitigate delays.

-Manage interfaces with other Time Schedulers, Functional and Project Groups such as Site Works, Procurement, Commissioning, contractors, and the Client, to identify and manage upstream and downstream impacts and relationships.

-Incorporate progress measurement and required resource levels into the completely integrated schedule analysis.

-Provide Primavera layouts to show the detailed Engineering time schedule, summary schedules, critical path, Client and licensing organization approval activities, with meaningful milestones to track the project’s status.

-Prepare and issue formal weekly and monthly reports and ad-hoc studies, analysis, and reports.

Experience Hours (Planning & Scheduling): 
3050
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
350