Projects Planning Engineer

Projects Planning Engineer, Arabian BEMCO Contracting Company, Qurayyah, Combine Cycle Power Plant, PP10 CCGT

START Date: 
April, 2011
END Date: 
March, 2015
Master schedule update and analysis. T&C schedule updating. Managed and coordinate subcontractors and other parties involve in the site with regards to completion datelines, resource planning and technical requirements. Managed planning documentations, systems and procedures including method statements. Monitor construction schedule execution on site and records completion of activities and milestones.

Projects Planning Engineer, Arnaout Contracting, DAMMAM, Turnkey construction for the new Weatherford Base located at Abqaiq Road

START Date: 
September, 2009
END Date: 
September, 2010

 

Scheduling, Project Invoicing and Change order tracking.

Project phase wise tracking and progress reporting system set up.

Estimates of manpower requirements made for project team.

Manage subcontracting procurement, contracts and schedule.

Projects Planning Engineer, Arnaout Contracting Est. , Dhahran District Cooling Plant, Saudi Aramco

START Date: 
September, 2010

 

a.   Project delay analysis presented and achieved time extension and claims

b.   Scheduling, Project Invoicing and Change order tracking.

c.   Contract adjustment negotiated for change in project objectives in terms of coordination with process contractor.

d.   Project recovery schedule made and executed.

Projects Planning Engineer, Arnaout Contracting Est. , Saudi Aramco East Dammam Development: Villas Construction

START Date: 
February, 2012

 

a.   Manage a team of two – Quantity surveyor and Planner.

b.   Resource and cost loaded schedule built in P6 for 228 villas with over 50,000 activities.

c.   Project phase wise tracking and progress reporting system set up.

d.   Estimates of shuttering and manpower requirements made for project team.

e.   Manage subcontracting procurement, contracts and schedule.

Projects Planning Engineer, AECOM, Arnaout Contracting Est., General Electric Dhahran Techno Valley Facility

START Date: 
April, 2012

a. Built WBS, project baseline schedule and track the progress. b. Project quality plan, Inspection and test plan, HSE Plan and procedures in full compliance with GE standards, project risk assessment and mitigation plan, risk monitoring documentation, detailed method statements for construction activities including MEP works.