Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Junior Planning Engineer

JUNIOR PLANNING ENGINEER, NAGARJUNA CONSTRUCTION COMPANY, C/o 2 Tier Underground Basement & all Ancillary Building Works for WEIGHT LIFTING AUDITORIUM

START Date: 
April, 2008
END Date: 
May, 2010

PLANNING & SCHEDULING OF PROJECT.(MS PROJECT 2007 & PRIMAVERA P6)

COST CONTROL & MIS REPORTING.

ADDITIONAL ROLE & RESPONSIBILITY :-  SINGLE POINT CONTACT PERSONNEL RESPONSIBLE FOR REPORTING & CONDUCTING WEEKLY AND MONTHLY MEETINGS AT SITE WITH CLIENT.

QUANTITY SURVEYOR & BILLING ENGINEER FOR RAISING CLIENT & SUB-CONTRACTOR BILLING.

Experience Hours (Planning & Scheduling): 
7800
Experience Hours (Cost Management): 
7500
Experience Hours (Forensic Analysis): 
7800

Junior Planning Engineer, Al-Hodeery Multi Activites Co, EPCC of the Marine Terminal

START Date: 
June, 2010
END Date: 
February, 2011

Establish and manage effectively a planning and progress control system in order to support the Project Manager decision-making process and allow him to complete the project according to the internal baselines and in compliance with the contractual dates and requirements. Ensure any deviation from plan is promptly spotted and analyzed, final time impact is  estimated.

Junior Planning Engineer, IVRCL Infrastructures & Projects Ltd, NAVAL academy project ezhimala , JBIC assisted drinking water supply project

START Date: 
June, 2007
END Date: 
September, 2010

Site monitoring and controlling.

Review of progress

Preparation of Bar Bending Schedules (BBS), Material reconciliation statements, Department bills, Preparation of Daily and monthly progress reports, etc.

junior planning engineer, ma kharafi , DLC hq buildings

START Date: 
October, 2011
END Date: 
October, 2013

*     Assisting the Planning Manager in preparation of the Updated Program.  

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
0

Junior Planning Engineer, SICIM SpA, construction of pipelines & other facilities in OIL&GAS processing plant

START Date: 
June, 2012

HI! My name is Shnara, I am from Kazakhstan. In june 2012 I've been promoted to junior planning engineer in SICIM SpA, our company deals with construction in oil & gas shpere, that is construction of facilities, pipelines, different repair works. We have different projects, so I am very lucky to have experience in various construction field :)   Our main projects are: construction of pipelines, repair of lines, construction of buildings, vessels, some civil & piping/mechanical scopes in operating plant Tengiz, under operation of Chevron company.    

Junior Planning Engineer, Dhabi Contracting LLC, 433 villas

START Date: 
October, 2011

working as junior planning engineer in Dhabi Contracting LLC in Abu Dhabi -Ghyasi Project - 433 villas 

Junior Planning Engineer, Al Geemi & Partners, Reem Island

START Date: 
May, 2012

Completed my Civil Engineering in 2011, and got lucky enough to work as a junior planner in a Claims project worth (350 million AED) my specific duties were

- assist the senior planner in critical path analysis

- responsible to create disruption events

- creating utility and window analysis to help the Contractor in mini Global Claims

- attended the International Arbitration Course and applied for Associate membership for CIArb result expected in June 2013.

Junior Planning Engineer , Mercury Engineering Services LLC, Oman Botanic Garden, Science & Technonolgy Park (Engineering Services)

START Date: 
October, 2009

WORK EXPERIENCE
===============
   October 2009 to Present
   Junior Planning Engineer
   MERCURY ENGINEERING SERVICES LLC
   Oman Botanic Garden - Sultanate of Oman

     * DUTIES & RESPONSIBILITIES:
        - Take off scope of materials for progress percentage update
          in the program schedule.             

Junior Planning Engineer, Intel , Intel Semiconductor Manufacturing Project

START Date: 
September, 1994
END Date: 
December, 1995

Worked on the Construction of Intel Fab 10 for Intel from December 1994 to December 1995. Responsible for set up of construction schedules for E&I Installation for Intel's new Fabrication Plant. Work on schedules was developed in Primavera P3 Version 1.0 (with a dongle - those were the days!) and progress measurement was performed in excel as was earned value analysis.