CIVIL / PLANNING ENGINEER, ENKA , Al TAIF University Buildings & Infrastructure

START Date: 
December, 2010
END Date: 
December, 2011

 

 

ENKA İnşaat ve Sanayi A.Ş., (Riyadh, Saudi Arabia)

Period:2011 Till Date.

Project:    

-WATER TRANSMISSION FROM HILI & YOBBA & AL-LITH DAMS TO AL-SHOUIBA    PLANT (PHASE 2) (KSA).

CIVIL / PLANNING ENGINEER, CCCL ltd , Elevated Metro Rail Station and Viaduct

START Date: 
March, 2011

Planning ¨ Scheduling ¨ Risk Management ¨ Earned value Analysis

Collecting inputs related to project plan preparation and preparing the baseline schedule.

Monitor critical path & overall schedule on a daily basis. Prepare catch up plans, look ahead plans based on inputs from respective sources and report to Project Manager.

Optimum utilization of resources, Adherence to targets.

Follow up with clients for construction, checking drawings and quantities and ensuring that the calculations are accurate for the work.

CIVIL / PLANNING ENGINEER, MT Hojgaard, Cable stayed bridge

START Date: 
April, 2010

Work Experience

1/ Rao II cable stayed bridge project (ODA project) - MT Hojgaad's Office management-Denmark Contractor- Apr 2010 - Present

Position: Planning Engineer.


- Preparation and control Master schedule, Production schedule, Weekly schedule in Cable stayed bridge project.

CIVIL / PLANNING ENGINEER, Saudi Oger Ltd., Office Buildings, Commercial and Residential Buildings

START Date: 
May, 2007

Assisting with the development and implementation of acceptable Planning and Scheduling methods and techniques.

CIVIL / PLANNING ENGINEER, ARAMCO-KJO THRU: BHSC, Replacement of Pipe Sleepers in GOSP, Replacement of Oil Tank Foundation and Dikes, Replacement of Machinery Foundation in Power Plants and Flare , Offshore Maintenance Works in Oil Rig / Platform, Minor C

START Date: 
July, 2006
END Date: 
August, 2008
  • Prepare project master schedule and project detailed schedules.
  • Monitoring and Controlling of the integrated schedule of all project activities including Civil, Mechanical and Electrical during the construction phase.
  • Prepare reports on Baseline vs Current Schedules plus analysis on forecast for weekly progress report to the top project management team.
  • Interface with Engineering, Construction and Commissioning activities to align activities according to plan
  • Preparation of float and critical path analysis
  • Issue Project Weekly/Monthly

CIVIL / PLANNING ENGINEER, QDVC (Qatari Diar Vinci Construction), Underground carparks and utility tunnels

START Date: 
January, 2000

Assisrant Planning Engineer: Project Schedule and Programme; Progress Update; Internal and Client Weekly Reports; Monthly reports

Market Place