Costain

Michael Scott

First Name: 
Michael
Last Name: 
Scott
Oldest experience: 
Feb 1978 (46.2 yrs experience, WARNING: 8.1 years variance with Professional Since)
Years Experience: 
35

Planning manager, Costain, Bradwell Power station decommissioning

START Date: 
March, 2011

Planning manager for Nuclear EPC contracts.  Role  involves forecating completion costs and dates.  Also preparing Client reports.

Senior Planner, Costain, Glen Eyre KLM, Southampton; Project Diamond, Didcot

START Date: 
March, 2003
END Date: 
June, 2005

Planner / Coordinator – Glen Eyre KLM, Southampton (traditional contract with CDPs):

Appointed to plan the £16m refurbishment and extensions to three 3-storey student accommodation buildings. Each had a steel framed single storey roof extension to provide a further floor of accommodation, and a concrete frame / blockwork and PC floor constructed 4-storey extension to the front.

The role involved the planning and monitoring of the design, procurement and construction processes from site start onwards.

Planning Engineer, Costain, Southern Water AMP 5

START Date: 
November, 2006
END Date: 
July, 2005

Programme managment of a suite of waste water treatment upgrades in the Sussex county.  Detailed programme development, cost profiling, and reporting.

Junior Planner, Costain, Berkeley Nuclear Power Station Decommissioning

START Date: 
July, 2011

Position: Planning Engineer with Costain on their nuclear decommissioning framework at Berkeley Power Station. 

 

The framework objective is to help Magnox put the decommissioned nuclear power station at Berkeley into ‘Care & Maintenance’.  To achieve this they are in the process of extracting all remaining ‘intermediate level waste’ and processing it ready for disposal at a geological disposal facility.  The framework contract is based on the NEC model.  My role as the site planner is fourfold:

Planning Manager, Costain, Port Ghalib - Marsa Alam Egypt

START Date: 
June, 2004
END Date: 
April, 2005

Working on the Multi million dollar new development of Port Ghalib a new Red Sea Resort Town and Marina in Egypt.

In charge of all aspect of the planning for the Construction work of a $250 millions 3 Hotels [385rooms], 3 swimming Pools, 70,000 m2 Sea water Lagoon, a 2nd Phase Marina Development, Retail Souq and a Corniche.

Principle Planning Manager, Costain, Various

START Date: 
April, 2007
END Date: 
January, 2009

Principle Planning Manager for the Midlands and Northern Regions of the UK, tender, contract and claims roles on a variety of construction projects.

Project Planner, Costain, M25 Holmesdale Tunnel

START Date: 
January, 2006
END Date: 
September, 2007

I was working as part of the construction site team in M25 Holmesdale Project, Enfield. The project is to refurbish tunnel structure on M25 junction 25, Holmesdale Tunnel. The scheme includes ground works, piling, demolition, construction of reinforced concrete walls and deck, and mechanical and electrical installation.

Senior Planner, Costain, Alba Potline aluminium smelter and associated works

START Date: 
September, 1990
END Date: 
December, 1991

 

1990 – 1991:  Costain, UK: Senior Planner

Bahrain, Gulf

Trevor Spencer

First Name: 
Trevor
Last Name: 
Spencer
Professional Since: 
Jul-2008 (15.8 yrs experience)
Oldest experience: 
Aug 2009 (14.7 yrs experience, WARNING: 1.1 years variance with Professional Since)
Years Experience: 
1

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content