Hi,
after several days self-training on Primavera Risk Analysis, I still can't simulate the following sequence:
-during an iteration, the activity duration is above its deterministic duration, pushing the succeeding milestone in delay.
- in that case, I would like to impact on PRA the schedule and costs in accordance with these 2 scenarios (previously chosen before starting the simulation, I mean only 1 scenario will apply during all iterations):
> SCENARIO 1 (RECOVERY PLAN, MILESTONE NOT IN DELAY) : more resources put in a certain durat