Schedule Risk and Schedule Risk Analysis

Software - Safran Risk, @Risk, Predict!

Hi all. How would you guys rank Safran Risk, @Risk and Predict! for carrying out QRA (both QSRA and QCRA)? On QSRA, I consider Safran Risk is the better one, as it is more comprehensive with more options. And it looks more promising to deal with complex risk model as well. However, i don't have much idea on QCRA. Thanks in advance. 

Multiple imports of risks to Primavera P6

Hi everyone,

Is there solution ti import (through Excel) risks to large number of activities in P6 schedule?

Similar to importing of activities and/or resources, I would like to define several different risks and then instead of using manual method in P6 to export file to Excel, then prepare it for importing by coping risks to different activities and return it through import.

I have tried it, but I can not find Risks in Available Options in Export dialogues.

 

Thank you in advance!

Monte Carlo Simulation Challenges

How to become a risk analyst

Hi everyone, 

I have been working as a scheduler and planner for a while and I am currently living in Australia

I am just trying to improve my knowledge and hopefully change of careers in the future.

Can anyone of you guys help me where to start from?

What would be the best course that I can take to gradually improve my knowledge.

Obviously I am not one of those who are trying to find the solution over night. I am seeking for change of career and improving my knowledge and learnin through this year.

QSRA - how often would be the best?

Hi everyone,

just wonder how often should QSRA be carried out? Are there any guideline/ reference book saying like 6 months cycle would be more appropriate? 

Thanks a lot. 

NASA RIDM Handbook SP-2010-576

Hi, has anybody used this handbook to inform their E&C Risk Processes? Seems highly technical and couched in risk language for the average risk planner.

thanks

Task Percentiles in Pertmaster

Anyone knowing how to deal with this warning (i.e. risk data is out of date) in Pertmaster?

Thank you so much.

8046
pertmaster.jpg

Need Guidance on Schedule Risk analysis

I have an updated schedule,

3. some activites are completed.

2. some have started but not completed

3. some not yet started.

I want to run a schedule risk analysis to no my probabilistic completion date. the schedule is not resource loaded.

 

whats the best approach to this

Primavera Risk Analysis - Getting the absolute minimum and maximum

Hi all,

 

I have a very detailed risk analysis for my project (different risks, different uncertainties with different distributions,...). And now I would like to see the "absolute" minimum and maximum end dates.

Ofcourse since Monte Carlo Analysis is based on random iterations, I can never say with certainty what the shortest project duration is (think extremely happy flow, all uncertainties getting the minimum durations). I get the minimum from OPRA but next time I run the simulation I might get a new minimum (or maximum).