Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Schedule Risk and Schedule Risk Analysis

Technical query about Pertmaster and Low Memory

As the subject indicates, I have encountered an issue whereby Pertmaster "runs out of memory" and will crash.  There is no loss of data, but after several attempts to continue is has slowed to a crawl. 

Does anyone, or has anyone encountered this issue, and developed a resolution?

 

Thanks in advance.

PRA Cost Roll Up

Hi,

In the Risk Outputs tab of PRA, the P50 cost does not seem to roll up properly. For example the sum of the P50 costs of activities do not always equal the P50 cost of their WBS element, and the sum of the P50 costs of WBS elements does not always equal the P50 cost of their parent WBS element. 

Has anyone else had this issue? 

Any assistance would be greatly appreciated.

Kind regards,

Simon 

XER WBS import errors

Has anyone encountered errors when importing a WBS IDs into Primaverea Risk Analysis (PRA).

Risk Management Strategies/Procedures

I'm a fan of Primavera Risk Analysis Risk Register. I think it could be an effective tool in managing risk. To that end, what have you see done, or do you do to effectively manage risk. What kind of followup do you do, or have seen to make sure the mitigation strategy is implemented? How often do you or have seen periodic risk reviews? Has anyone published procedures for systematic risk management? A lot of questions.

Exporting P6 R 15.1 Risk Register to PRA

Can anyone point me to the instructions to use the Risk Register generated in P6 to populate the Risk Register in PRA? Is it possible? Thanks.

Best Risk Register

Is there a better risk register than the Primavera Risk Analysis register? Thanks.

PhD Thesis & Scientific Paper on Risk Management in the Middles East

Gents,

             The following links are for a PhD and a scientific paper in the construction risks in the Middle East. The Thesis shows the methodology of how to overcome the risks and delays on construction projects and how estimate the durations of activities and consequently forecasting the project's duration while considering the degrees of uncertainty.

It is my great honor to share the thesis and the paper with you. Also, please feel free to share them with whomever is concerned.

 

Theory of chance

FYI: There's a U Penn Coursera course that looks promising.

https://www.coursera.org/course/probability

Too early to tell how it will end - chance? It may be worth you time. Thought you should know. Good luck. Happy learning.

Pertmaster > Primavera Risk Analysis

Hello everyone,

Im new in the using of the Primavera Risk Analysis program and i have lefted my eyes in the internet searching for tutorials or a good ebook / book to learn by myself how to use it, if anyone knows or have some papers or information i would really apreciate the help! (my boss its making me crazy because he want me to know how to use the program) 

Thanks! 

Full Monte 2014 for P6 Version 1.1 Now Supports SQLite

Primavera Risk Analysis does not yet support SQLite, but Barbecana latest release of Full Monte 2014 for P6 Version 1.1 does now support SQLite http://ow.ly/FmTMA

Market Place

No results found... (try selecting a different content filter)

Syndicate content